New Campus of the University Hospital in Krakow (Prokocim)

completedstage: operationaldelivereddelayed
PLN 1.2 billion
programme budget (multi-year) · data from 2019net or gross: not recorded≈ PLN 1.2 billion (value-by-stage, est., nominal)funding: state funds, EU funds, the investor’s own fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The new campus of the University Hospital in Krakow is a hospital complex built in the Prokocim district, ranked among the largest of its kind in Poland. On a site of nearly 15 hectares, a group of medical buildings was erected housing approximately 925 beds, clinical departments, specialist outpatient clinics, and an integrated operating suite with 24 rooms. The investor was Jagiellonian University – Collegium Medicum; the construction contract was signed in January 2015, and the official opening took place on 29 October 2019. The total cost exceeded PLN 1.2 billion, of which PLN 800 million came from the state budget.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[3]
Scheduledelayed[3]
Utilisationin use[7]
hospitalizations per year in the entire hospital, whose core is the Prokocim campus (25 of 33 clinical wards)
Current
102 270 hospitalizations/yr (2025)
Capacity or target
kompleks projektowany na ok. 925 łóżek / 24 sale operacyjne

Timeline

Slip: under a year (given as a year)

  1. Construction start2015
  2. Last stated dateMay 2019
  3. Delivery2019

Change history

  • 29 Oct 2019stage: operational

Significance

Relocating and centralising the clinics on a modern campus in Prokocim replaced dispersed, partly historic buildings in the centre of Krakow, increasing the region's bed base and its diagnostic and treatment capabilities. The facility became one of the largest and most modern hospital investments in Poland and a point of reference for subsequent major healthcare projects.

Sources 7 · 5 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. inzynieria.com29 Oct 2019
    Cost
    CostCała inwestycja pochłonęła ponad 1,2 mld zł
  2. RMF2429 Oct 2019
    InvestorFunding
    InvestorCollegium Medicum UJ i szpitala
    Locationprzy ul. Jakubowskiego w Krakowie Prokocimiu
    FundingJej koszt to ponad 1,2 mld zł, z czego 800 mln zł pochodzi z budżetu państwa
    Funding255 mln zł z regionalnego programu operacyjnego województwa małopolskiego
    Fundinga reszta to własne pieniądze Collegium Medicum UJ i szpitala
  3. Magiczny Kraków (krakow.pl)29 Oct 2019
    StatusStageDeliverySchedule
    Status · Stage · Delivery · ScheduleWe wtorek, 29 października otworzono nową siedzibę Szpitala Uniwersyteckiego w Krakowie.

    year taken from the source's publication date (29 Oct 2019)

  4. Przegląd BudowlanyOct 2018
    Construction startLast stated date
    Construction startNa plac budowy wkroczyliśmy w lutym 2015 roku.
    Last stated datea jej koniec przewidywany jest na koniec maja roku 2019.