New Seat of the Polish Army Museum at the Warsaw Citadel

completedstage: operationaldelivereddelayed
PLN 256 million
contract value · data from 2018net or gross: not recorded≈ PLN 256 million (value-by-stage, est., nominal)planned funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The new, permanent seat of the Polish Army Museum, being built on the grounds of the Warsaw Citadel, designed by the Warsaw studio WXCA. Construction of the building (the south building) started in March 2018, and on 13 August 2023 the first completed part of the new seat was ceremonially opened, giving the Polish Army Museum, an institution in existence since 1920, its own permanent building for the first time. The general contractor for the building was a consortium of IDS-BUD S.A. and MAR-BUD Budownictwo, whose tender offer came to just under PLN 256 million (the contracting authority had earmarked up to PLN 320 million gross for the task); construction was financed from a grant from the Ministry of National Defence, and the cost of the permanent exhibition was estimated separately at approximately PLN 45 million. The new seat of the Polish Army Museum, together with the neighbouring building of the Museum of Polish History, forms the Citadel of Museums complex being built at the Citadel; the total construction cost of both museums was put at PLN 821 million. According to findings by the Supreme Audit Office (NIK), the multi-year programme for 2009-2018 allocated PLN 485.5 million for the construction of the Polish Army Museum, and the completion deadline was pushed back several times (originally 2012, then 2021). The Polish Army Museum complex is ultimately to be complemented by a north building, to be carried out in a second stage.

How it went

Assessment: provisional, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[2]
Scheduledelayed[5]

Timeline

  1. Construction startMar 2018
  2. Delivery2023

Change history

  • 13 Aug 2023stage: operational
  • Mar 2018stage: construction

Significance

The opening of the new seat at the Warsaw Citadel gave the Polish Army Museum, in existence since 1920, its own permanent exhibition space for the first time in its history, after more than a hundred years of operating without a building of its own. The new seat, together with the neighbouring Museum of Polish History, forms the Citadel of Museums, one of the largest museum complexes being built in Poland. The investment was part of a multi-year programme financed by a grant from the Ministry of National Defence, under which PLN 485.5 million was planned for the construction of the museum (NIK findings); implementation proceeded with a multi-year delay relative to the originally assumed deadlines.

Sources 6 · 5 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Kultury i Dziedzictwa Narodowego (gov.pl)Aug 2023
    Construction start
    Construction startBudowa nowego gmachu Muzeum na terenie Cytadeli Warszawskiej rozpoczęła się w marcu 2018 roku.
  2. PropertyDesign.plAug 2023
    StatusStageDelivery
    Status · Stage · Delivery13 sierpnia 2023 r. uroczyście otwarto nową jednostkę muzealną na terenie Cytadeli Warszawskiej.
  3. dzieje.pl (PAP)22 Mar 2018
    CostInvestor
    Costoferta konsorcjum IDS-BUD S.A. oraz MAR-BUD Budownictwo Spółka z ograniczoną odpowiedzialnością Sp. k. - informuje Muzeum. Konsorcjum to zaoferowało za wykonanie zamówienia cenę niespełna 256 mln zł
    InvestorBudowa Muzeum Wojska Polskiego w Cytadeli jest finansowana z dotacji Ministerstwa Obrony Narodowej
  4. Polska ZbrojnaNov 2019
  5. Najwyższa Izba Kontroli (NIK)Apr 2021P/20/034/KON
    FundingSchedule
    FundingNIK ustaliła, że MON zapewniało środki na budowę Muzeum i rozliczenie wykonywanych prac.
    ScheduleNIK zwraca uwagę na nieterminowość procesu inwestycyjnego. Zgodnie z pierwotnymi założeniami MWP miało być ukończone w 2012 r.
  6. dzieje.pl (PAP)18 Jan 2018