Polish History Museum at the Warsaw Citadel
The new headquarters of the Polish History Museum being erected on the grounds of the Warsaw Citadel at ul. Gwardii 1 in Warsaw. The building, with an area of over 44,000 m2, was designed by the Warsaw studio WXCA, and the general contractor was Budimex. Construction works began on 6 July 2018, the building was completed in 2023, and from 29 September 2023 it was opened to visitors with temporary exhibitions. The permanent exhibition presenting the history of Poland is being created across eight thousand square metres and is to gather over three thousand exhibits; the museum's management plans to open it on 4 June 2027. According to the findings of the Supreme Audit Office (NIK), the total cost of the project together with the permanent exhibition will exceed PLN 1.2 billion, many times more than the originally assumed deadline and budget from 2015.
How it went
Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section
Timeline
Slip: +91 mo. vs. the original date
- Construction start6 Jul 2018
- Original dateNov 2019
- Current date4 Jun 2027
Change history
- 6 Jul 2018stage: construction
Significance
The investment is one of the largest and most costly ventures in the area of Polish culture: according to NIK, the total cost together with the permanent exhibition will exceed PLN 1.2 billion, many times more than assumed when the government adopted the programme in 2015 with a completion deadline of November 2019. The state audit pointed to a threefold postponement of the investment completion date and successive changes to the multi-year programme. The new headquarters at the Citadel gives the Polish History Museum its own, permanent exhibition space and makes it a key institution of the state's historical narrative.
Sources 6 · 4 independent · 6 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.
- Najwyższa Izba Kontroli (NIK)2023P/22/018/KNOConstruction startStage historyOriginal dateFundingSchedule
Construction start · Stage history6.07.2018 r. rozpoczęcie robót budowlanych
Original dateRząd uchwalił program w lipcu 2015 r., wyznaczając termin realizacji na listopad 2019 r.
Fundingrząd wystąpił do Komisji Europejskiej o zatwierdzenie 1,2 mld zł dotacji w ramach pomocy publicznej na budowę Muzeum Historii Polski
ScheduleOpóźnienia dotyczyły każdego z kolejnych etapów zadania – zarówno działań przygotowawczych i prac projektowych, jak i budowy.
- Najwyższa Izba Kontroli (NIK)2023Cost
Costkoszty realizacji projektu (wraz z wystawą stałą) przekroczą 1,2 mld zł
- Muzeum Historii Polski2018
- Wikipedia (pl)InvestorOwner type
Investor · Owner typeAkt powołania i statut placówki podpisał tego samego dnia na Zamku Królewskim w Warszawie Minister Kultury i Dziedzictwa Narodowego Kazimierz Michał Ujazdowski
Locationul. Gwardii 1 01-538 Warszawa
- [5]Trzy tysiące eksponatów w sześciu galeriach. Powstaje wystawa stała Muzeum Historii Polski ↗archived ✓TVN24 Warszawa14 May 2026StatusStageCurrent date
Status · Current dateDyrekcja MHP planuje otworzyć podwoje dla zwiedzających w 38. rocznicę wyborów 4 czerwca 1989 roku.
StageEkspozycja powstaje na drugim piętrze budynku i zostanie podzielona na sześć epok
- Murator PlusSep 2023Delivery
NameBudynek Muzeum Historii Polski został zaprojektowany przez pracownię architektoniczną WXCA, która w 2009 roku zwyciężyła konkurs na koncepcję.
DeliveryLicząca 1400 m² sala wystaw czasowych będzie sercem wystawienniczej działalności Muzeum do czasu otwarcia w 2026 roku wystawy stałej.