Municipal Waste Thermal Treatment Plant (ITPOK) in Poznań

completedstage: operationaldelivered
PLN 832 million
contract value · data from 2016net or gross: not recorded≈ PLN 832 million (value-by-stage, est., nominal)funding: EU funds, private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Municipal Waste Thermal Treatment Plant (ITPOK) on Gdyńska Street in Poznań, built and operated under a public-private partnership (PPP), in which the public partner is the City of Poznań and the private partner is PreZero Zielona Energia sp. z o.o. (formerly SUEZ, and before that SITA Zielona Energia). The public-private partnership agreement was signed on 8 April 2013. Construction work started on 16 April 2014 and finished on 15 January 2016, and the plant has been in operation since 30 December 2016. The total investment cost was approximately PLN 832 million. The project used what is known as hybrid financing, combining the private partner's own funds (a loan from a consortium of banks that included PKO Bank Polski) with an EU grant of PLN 330 million, secured by the City of Poznań under the Operational Programme Infrastructure and Environment for 2007-2013. The plant thermally treats mixed municipal waste, producing electricity and heat. The project is described as the largest investment in Poland's history carried out under the PPP model.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Scheduleon time[4]
Budgeton budget[3]

Timeline

  1. Announced8 Apr 2013
  2. Construction start16 Apr 2014
  3. Delivery30 Dec 2016

Change history

  • 30 Dec 2016status: completedOd 30 grudnia 2016 r. rozpoczęto eksploatację instalacji.
  • 30 Dec 2016stage: operational
  • 16 Apr 2014stage: construction

Significance

ITPOK completes Poznań's waste management system, providing thermal treatment of mixed municipal waste instead of landfilling it, with the recovery of electricity and heat. The investment is cited as the largest project in Poland's history carried out under a public-private partnership, and as a pioneering example of hybrid financing, combining the private partner's capital with an EU grant (PLN 330 million from the Operational Programme Infrastructure and Environment 2007-2013). This model became a reference point for later municipal waste thermal treatment plants in Poland.

Sources 4 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Miasto Poznań (poznan.pl)
    StatusStageCostAnnouncedConstruction startDeliveryInvestorFunding
    Status · Stage · Deliveryod 30 grudnia 2016 roku nastąpiło rozpoczęcie eksploatacji Instalacji.
    CostŁączny koszt inwestycji to ok. 832 mln zł.
    Announcedumowy o partnerstwie publiczno-prywatnym, zawartej w dniu 8 kwietnia 2013 r. pomiędzy Miastem Poznań, a PreZero Zielona Energia sp. z o.o.
    Construction startPrace budowlane rozpoczęły się dnia 16.04.2014 r., a zakończyły 15.01.2016
    Investorumowy o partnerstwie publiczno-prywatnym, zawartej w dniu 8 kwietnia 2013 r. pomiędzy Miastem Poznań, a PreZero Zielona Energia sp. z o.o. (dawniej: SUEZ Zielona Energia sp. z o.o.)
    FundingMiasto Poznań pozyskało dofinansowanie z Unii Europejskiej w kwocie 330 mln zł w ramach Programu Operacyjnego Infrastruktura i Środowisko na lata 2007-2013.
  2. Bankomania (PKO Bank Polski)30 Mar 2017
    Funding
    FundingKonsorcjum banków, w skład którego wszedł PKO Bank Polski, udzieliło spółce SUEZ Zielona Energia kredytu w wysokości 878 mln zł.
  3. Gramwzielone.pl30 Mar 2017
    Budget
    BudgetTo przykład pierwszego w Polsce hybrydowego PPP, zakończonego w terminie i założonym budżecie.
  4. Schedule
    SchedulePoznańska spalarnia zbudowana została zgodnie z terminem założonym w umowie z Miastem Poznań.