An offshore wind farm project with a capacity of approximately 350 MW, planned in the Polish part of the Baltic Sea, approximately 50 km north of Ustka, in the western part of the Słupsk Bank. The project was developed by the German group RWE (through the company RWE Offshore Wind Poland) and subsequently sold to Polska Grupa Energetyczna: a conditional agreement was announced in December 2025, and the transaction was finalised on 10 March 2026, making PGE the sole owner. PGE intends to combine F.E.W. Baltic II with the neighbouring Baltica 9 project (975 MW), creating a joint Baltica 9+ complex with a total capacity of approximately 1.3 GW (approx. 1,325 MW), planned for completion by 2032 and serviced from PGE's service base in Ustka. RWE withdrew from the project, concluding that PGE is better prepared to carry it out.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Change history
- 3 Dec 2024stage: permits
Significance
After being combined with the neighbouring Baltica 9 project, F.E.W. Baltic II is to co-create the Baltica 9+ offshore wind farm complex with a capacity of approximately 1.3 GW, one of the largest planned offshore ventures on the Polish Baltic. The acquisition of the project from RWE strengthens PGE's position in the development of offshore wind energy and the achievement of Poland's energy transition goals.
Sources 8 · 5 independent · 7 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- RWE10 Mar 2026
Locationapproximately 50 kilometres from shore, north of the Polish town of Ustka
- offshoreWIND.biz13 Mar 2026StatusInvestor
StatusThe offshore wind farm is planned to be built around 50 kilometres north of the Polish town of Ustka
InvestorBaltic II offshore wind project in the Polish Baltic Sea to PGE Polska Grupa Energetyczna (PGE), making the Polish utility the sole owner of the 350 MW project. The offshore wind farm is planned to be built around 50 kilometres north of the Polish town of Ustka.
- [3]PGE wins offshore auction and acquires RWE project. Baltica 9+ giant to be established in the Baltic Sea ↗archived ✓BalticWind.EU13 Mar 2026
- Gramwzielone.pl11 Mar 2026
- RWE3 Dec 2024Stage
StageThe Voivode of West Pomerania has issued two key decisions to enable the F.E.W. Baltic II offshore wind farm to proceed.
- Funding
FundingThe Polish Energy Regulatory Office has awarded a Contract for Difference (CfD) to the F.E.W. Baltic II offshore wind project, which will have a planned installed capacity of 350 megawatts (MW).