BC-Wind Offshore Wind Farm

under constructionstage: construction
EUR 2.0 billion
programme budget (multi-year) · data from 1 Dec 2025net or gross: not recorded≈ PLN 8.6 billion (value-by-stage, est., nominal)funding: multilateral development bank, foreign loan, private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

An offshore wind farm with a capacity of up to 390 MW under construction in Poland's exclusive economic zone of the Baltic approximately 23 km north of the shore, off the municipalities of Krokowa and Choczewo in Pomorskie Voivodeship. The investor is Ocean Winds, a joint venture owned in equal shares by EDP Renewables and ENGIE. The project comprises 26 turbines of 14 MW each with a Power Boost function increasing capacity to 15 MW. In December 2025 the investor reached financial close, securing approximately EUR 2 billion of financing and moving from the development phase to the construction phase. Onshore works are to begin in 2026, and the first energy is expected in 2028.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction start2026
  2. Original date2028
  3. Current date2028

Change history

  • 1 Dec 2025stage: construction
  • 2025stage: permits

Significance

BC-Wind is Ocean Winds' first offshore wind project in Poland and one of the projects of the so-called first phase of Polish offshore. The target capacity of up to 390 MW will increase the share of renewable sources in the national energy mix and strengthen Poland's energy transition. The project uses Polish ports (Świnoujście as the assembly port for foundations, Gdańsk for turbines) as well as a service base in Władysławowo, engaging domestic contractors.

Sources 5 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ocean Winds1 Dec 2025
    StatusStage historyCurrent dateCostFunding
    NameBC-Wind is an offshore wind project developed by Ocean Winds in the Polish Exclusive Economic Zone of the Baltic Sea
    StatusThis achievement marks a key milestone, confirming the project’s readiness to move from the development phase into construction.
    Stage historyWarsaw, 01.12.2025: Ocean Winds, international company dedicated to offshore wind energy and established as a 50-50 joint venture between EDP Renewables and ENGIE, has secured an around €2 billion project finance and reached Financial Close for its first offshore wind farm in the Baltic Sea.
    Current dateexpected to deliver its first power in 2028
    CostAround €2 billion of project finance investment is secured to complete the construction
    Locationapproximately 23 kilometers north of the coastline, near the municipalities of Krokowa and Choczewo in the Pomeranian Voivodeship
    FundingThe project finance of BC-Wind is supported by the European Investment Bank (EIB), contributing to close to one third of the entire project finance, ICO (Instituto de Crédito Oficial Español) and 13 commercial banks, reflecting the maturity and long-term stability of the investment.
  2. Offshore Wind (offshorewind.biz)1 Dec 2025
    Original dateInvestor
    Original dateThe wind farm is expected to deliver its first power in 2028
    InvestorOcean Winds, a 50-50 joint venture between EDP Renewables and ENGIE
  3. BC-Wind / Ocean Winds
    Stage historyStage
    Stage historyIn 2025, construction permits were obtained for both the offshore and onshore parts, and the Final Investment Decision (FID) was made, marking the start of the construction phase
    StageBC-Wind is currently in the construction phase.
  4. Baltic Wind2 Dec 2025
  5. Ocean Winds23 Mar 2026
    Construction start
    Construction startWe have inaugurated at CRIST Offshore the production phase of the offshore substation for the BC-Wind project with a symbolic steel cutting ceremony, marking the project’s entry into the next stage of execution.

    Produkcja morskiej stacji elektroenergetycznej w stoczni CRIST; roboty na lądzie i na morzu to osobne części budowy.