Baltica 3 is the second phase of the Baltica offshore wind farm in the Polish Baltic, with a planned capacity of approx. 1045 MW, implemented by the PGE Baltica company as part of a joint venture of PGE and Ørsted (50 percent each). The farm is to be built in the part of the Baltic between Łeba and Ustka, at least 25 km from the shore. The project holds a location decision, an environmental decision and permits for connection infrastructure, but a final investment decision (FID) has not been taken for it. Commissioning was originally planned for 2026. In October 2025 PGE Baltica said the project had been suspended at one point and was undergoing deep economic optimisation, and that the company would like to return to the contracting phase as soon as possible. In May 2026 Ørsted confirmed that Baltica 3 was still in the optimisation phase and that further decisions on the project's future depend on market, regulatory and investor conditions. No current source gives a commissioning date, so the record assigns none.
How it went
Assessment: too early to assess, as of 1 Sep 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
- Original date2026
Significance
Baltica 3, as the second phase of the Baltica complex (together with Baltica 2, approx. 2.5 GW), is to add approx. 1045 MW of installed capacity in offshore wind energy, supporting Poland's energy transition and the diversification of generation sources in the Baltic. Separating the investment decision from Baltica 2 shifted this phase in time relative to the original plans, and after the project was suspended and put through economic optimisation its schedule remains unresolved.
Sources 11 · 9 independent · 9 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Pulsarowy.plInvestorOriginal date
InvestorProjekty Baltica 2 i Baltica 3 realizowane są przez PGE Baltica w partnerstwie joint venture z duńską firmą Ørsted
Original dateUruchomienie pierwszego etapu projektu Morskiej Farmy Wiatrowej Baltica, czyli Baltica 3 o mocy ok. 1045 MW, planowane jest zgodnie z harmonogramem na 2026 roku.
- offshoreWIND.biz30 Jan 2025StatusDelivery
Status · DeliveryBaltica 3 is planned to be fully operational by the end of the decade.
- Wizja LokalnaStage
Stagebudowa infrastruktury przyłączeniowej MFW Baltica-3 – lądowa stacja transformatorowa
LocationBaltica, której udziałowcami są PGE i Ørsted, powstanie w części Bałtyku między Łebą a Ustką.
- Baltica (PGE / Orsted)
- PGE Baltica
- Funding
FundingPrezes URE wydał trzy pierwsze decyzje o przyznaniu prawa do pokrycia ujemnego salda dla trzech projektów farm wiatrowych na Bałtyku. To wsparcie dla morskich farm przyznawane w ramach tzw. I fazy wsparcia w drodze decyzji administracyjnej Regulatora. Jak poinformował w środę URE, wydane decyzje dotyczą dwóch projektów PGE i duńskiego Orsteda - Baltica 2 o mocy 1498 MW, oraz Baltica 3 o mocy 1045 MW.
- Funding
FundingThe European Investment Bank (EIB) has approved the in-principle financing of the Baltica OWF project to be implemented by the PGE Group.
- [10]PGE Baltica chce jak najszybciej wrócić do kontraktacji Baltica 3; rynek offshore się stabilizuje ↗archived ✓Bankier.pl (depesza ISBnews)1 Oct 2025StatusStage
StatusProjekt swego czasu został wstrzymany, dzisiaj poddawany głębokiej optymalizacji ekonomicznej.
StageChcielibyśmy z tym projektem jak najszybciej wrócić do fazy kontraktacji, korzystając z szans, które widzimy, że otwierają się na rynku dostaw dla morskiej energetyki wiatrowej
- Bankier.pl (depesza ISBnews)14 May 2026