Baltica 1 offshore wind farm

plannedstage: permits

A planned offshore wind farm with a capacity of about 900 MW (0.9 GW), located in the Polish part of the Baltic Sea about 80 km from the shore, off Łeba in the Pomorskie Voivodeship, developed by PGE Baltica of the PGE Polska Grupa Energetyczna company. The project belongs to the second, auction phase of Polish offshore wind energy. By 2025 it had obtained an environmental decision, a location permit and a grid connection agreement, and it entered the first Polish offshore auction (contracts for difference), settled on 17 December 2025. In this auction, the Baltica 1 bid with a capacity of 896 MW did not obtain support – contracts for difference were awarded to three other projects (Baltica 9, Baltic East and Bałtyk I) with a combined capacity of 3.435 GW. Commissioning of the farm was planned by the end of 2032, provided the auction was won; following the unsuccessful auction, the further implementation path remains open.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Original date2032

Change history

  • Nov 2025stage: permits

Significance

Baltica 1 is one of three offshore wind energy projects developed by the PGE group in the Polish Baltic; once fully implemented, the farm with a capacity of about 900 MW would increase national generation capacity from renewable energy sources. However, the failure to be awarded a contract for difference in the first offshore auction of December 2025 delays the financing model and commissioning of the project, whose further implementation depends on subsequent market outcomes.

Sources 5 · 5 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. offshoreWIND.biz4 Nov 2025
    StageStage historyInvestorOriginal date
    StageThe project already has a location permit and a connection agreement.
    Stage history · InvestorPGE Polska Grupa Energetyczna (PGE) has obtained environmental approval for its 900 MW Baltica 1 offshore wind project
    Original dateBaltica 1 is planned to be commissioned by the end of 2032 if it secures a Contract for Difference (CfD) in this year's Polish offshore wind auction.
    LocationThe wind farm is situated some 80 kilometres from the coastline, roughly off the town of Łeba in the Pomeranian voivodeship.
  2. Gramwzielone.pl4 Nov 2025
  3. BalticWind.EU18 Dec 2025
    Status
    StatusAn additional bid was submitted for the Baltica 1 project with a capacity of 896 MW, but it did not secure support in this auction round.
  4. Energy Regulatory Office (URE)18 Dec 2025
  5. Notes From Poland19 Dec 2025