🛡Defencestrategic

MikroSAR – SAR radar satellites for the Polish Army

completedstage: operationaldelivered
PLN 860 million
contract value · data from 14 May 2025incl. VAT≈ PLN 860 million (value-by-stage, est., nominal)funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The Armament Agency's purchase of a satellite radar reconnaissance system for the Polish Army. The contract, worth approx. PLN 860 million gross and signed on 14 May 2025 with a consortium of ICEYE Polska and Wojskowe Zakłady Łączności Nr 1, covered three SAR satellites with an option for a further three, as well as a mobile ground segment. The first satellite reached orbit on 28 November 2025 (Transporter-15 mission), two more on 30 March 2026 (Transporter-16), and a fourth – the first of the exercised contract options – on 3 May 2026 (Falcon 9 from Vandenberg base). In total four satellites were placed in orbit, and on 15 May 2026 the system was officially handed over to the Polish Armed Forces.

How it went

Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, 2 have an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Scopeas announced[6]

Timeline

  1. Construction start14 May 2025
  2. Original date2026
  3. Last stated date2026
  4. Delivery15 May 2026

Change history

  • 15 May 2026stage: operational
  • 28 Nov 2025stage: commissioning
  • 14 May 2025stage: construction

Significance

The first sovereign satellite radar reconnaissance system of the Polish Army, operated by the Geospatial Reconnaissance and Satellite Services Agency (ARGUS). The SAR radars image terrain with an accuracy reaching approx. 25 cm per pixel and work both by day and by night as well as despite cloud cover, which reduces the army's dependence on foreign sources of reconnaissance data. The programme was carried out in approx. a year from the signing of the contract – with four satellites launched into orbit – which the defence ministry presents as one of the fastest completed acquisitions in the history of the Polish army.

Sources 8 · 4 independent · 7 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Obrony Narodowej (gov.pl)15 May 2026
    StatusConstruction startDeliveryInvestorStage historyStage
    Status · Delivery · StageOd momentu zakupu do osiągnięcia gotowości operacyjnej przez jednostkę ARGUS minął zaledwie rok, w trakcie którego wyniesiono na orbitę cztery satelity radarowe.
    Construction start · Stage historyUmowa zawarta 14 maja 2025 roku
    Delivery · Stage history15 maja 2026 roku w Muzeum Wojska Polskiego, wicepremier i minister obrony narodowej Władysław Kosiniak-Kamysz oraz sekretarz stanu w MON Cezary Tomczyk wzięli udział w uroczym przekazaniu Siłom Zbrojnym RP systemu satelitarnego rozpoznania radarowego MikroSAR.
    Investorfirmę ICEYE Polska, lidera konsorcjum, w skład którego wchodzą również Wojskowe Zakłady Łączności Nr 1 S.A. (PGZ)
  2. ICEYE15 May 2026
  3. ICEYE14 May 2025
    CostDescription
    CostWartość całego zamówienia wynosi ok. 860 mln zł brutto.
    Descriptionopcję zakupu kolejnych trzech satelitów i segmentu naziemnego w ciągu 12 miesięcy.
  4. Space2414 May 2025
    Original dateLast stated dateFundingInvestor
    Original date · Last stated datezaś start kolejnych jest przewidziany na 2026 r.
    Funding · Investor14 maja br. Agencja Uzbrojenia podpisała umowę na dostawę dla Wojska Polskiego Satelitarnego Systemu Obserwacji Ziemi w programie MikroSAR.
  5. Space2428 Nov 2025
    Stage history
    Stage history28 listopada br. firma SpaceX przeprowadziła start misji Transporter-15.
  6. ICEYE30 Mar 2026
    DescriptionScope
    Descriptionzaledwie 10 miesięcy po podpisaniu kontraktu, ICEYE dostarcza wszystkie satelity przewidziane w podstawowym zakresie programu
    ScopeTym samym, zaledwie 10 miesięcy po podpisaniu kontraktu, ICEYE dostarcza wszystkie satelity przewidziane w podstawowym zakresie programu.
  7. PAP13 May 2025
  8. Space243 May 2026
    Description
    Description3 maja br. o godz. 9:00 czasu polskiego firma SpaceX przeprowadziła start rakiety Falcon 9.