Nowa Wieś Ełcka energy storage facility (BESS Ełk, 200 MW / 800 MWh)

under constructionstage: commissioning
PLN 613 million
programme budget (multi-year) · data from Jan 2026net or gross: not recorded≈ PLN 613 million (value-by-stage, est., nominal)funding: capacity market, National Recovery PlanLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A large-scale battery energy storage system (BESS) with a power of 200 MW and a capacity of 800 MWh located in Nowa Wieś Ełcka in the Warmińsko-Mazurskie Voivodeship. The investment is being carried out by the Portuguese company Greenvolt, and the installation's components were supplied by BYD Energy Storage. The storage facility was connected to the 220 kV transmission grid of Polskie Sieci Elektroenergetyczne and was undergoing the energisation stage in mid-2026, becoming one of the largest installations of its kind in Europe. According to the EU funding map, the total project value is PLN 612.7m, of which PLN 213.6m is a non-repayable KPO grant. The project has secured capacity market contracts effective from 2028.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Change history

  • Jun 2026stage: commissioning

Significance

The installation, with a power of 200 MW and a capacity of 800 MWh, is among the largest battery energy storage facilities in Poland and Europe, supporting the stabilisation of the national power system amid the growing share of renewable sources. Connection to the 220 kV PSE transmission grid and capacity market contracts from 2028 place the facility within the expansion of large-scale energy storage in Poland.

Sources 8 · 6 independent · 1 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Gramwzielone.plJun 2026
    Stage historyInvestorOwner typeFunding
    Stage historyZostał podłączony do sieci 220 kV należącej do Polskich Sieci Elektroenergetycznych
    Investor · Owner typeInwestycję realizuje portugalska firma Greenvolt
    LocationNowej Wsi Ełckiej w województwie warmińsko-mazurskim
    Namemagazyn energii w Nowej Wsi Ełckiej ma 200 MW zainstalowanej mocy i 800 MWh pojemności
    FundingDla obu magazynów energii Greenvolt zabezpieczył 17-letnie kontrakty na rynku mocy
  2. Gramwzielone.pl2 Jul 2026
    StatusStage
    StatusMagazyn energii Greenvolt w Nowej Wsi Ełckiej o mocy 200 MW i pojemności 800 MWh obecnie przechodzi etap energetyzacji i według dotychczasowych danych należy do największych tego typu instalacji w Europie.
    StageMagazyn energii Greenvolt w Nowej Wsi Ełckiej o mocy 200 MW i pojemności 800 MWh obecnie przechodzi etap energetyzacji
  3. GreenvoltJul 2026
  4. Energetyka2431 Jul 2026
    Status
    StatusW Ełku powstaje magazyn o takich samych parametrach jak instalacja w Turośni Kościelnej — 200 MW mocy i 800 MWh pojemności.
  5. Evertiq (wydanie polskie)4 Mar 2025
  6. Green-news.pl31 Jul 2026
    StatusInvestor
    Status · InvestorIdentyczna instalacja powstaje w Nowej Wsi Ełckiej – tam Greenvolt buduje magazyn o tych samych parametrach, który zostanie podłączony do sieci 220 kV.
  7. Mapa dotacji UE (gov.pl)
    CostFunding
    Costwartość projektu 612 740 635,71 zł
    Fundingdofinansowanie z UE 213 580 937,83 zł
  8. Greenvolt Power27 Jan 2026
    Cost
    CostCałkowity koszt realizacji Przedsięwzięcia: 612 740 635,71 PLN