460 MW power generating unit (supercritical CFB) at Łagisza Power Station
The 460 MW unit at the Łagisza Power Station in Będzin (Łagisza district) was the world's first power generating unit with a CFB boiler (circulating fluidised bed) operating at supercritical parameters. The boiler was supplied by Foster Wheeler. The foundation stone was laid and the construction site consecrated on 12 May 2006, and the handover-to-service protocol for the unit was signed on 27 June 2009. The investor was Południowy Koncern Energetyczny S.A. (now TAURON Wytwarzanie S.A.). Ranked among the largest investments in the Polish power sector, it cost around PLN 2 billion, though construction was completed below the planned budget, at a cost of around PLN 1.9 billion. The unit is fired with hard coal and achieves a gross efficiency of no less than 45%.
How it went
Assessment: settled, as of 2009. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section
- Current
- blok przekazany do eksploatacji 27 czerwca 2009 r. i pracujący w Elektrowni Łagisza
- Capacity or target
- 460 MW
Timeline
- Construction start12 May 2006
- Delivery27 Jun 2009
Significance
The 460 MW unit at Łagisza was the world's first power generating unit fitted with a CFB fluidised-bed boiler operating at supercritical parameters, making it a model, reference installation for this technology in coal-fired power generation. Its high efficiency (no less than 45% gross) and its ability to burn hard coal, coal sludge and biomass reduced fuel consumption and emissions compared with older units. The investment was one of the largest in the Polish power sector during this period.
Sources 4 · 3 independent · 2 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Wikipedia (pl)StatusStageConstruction startInvestor
Status · StageBlok został przekazany do eksploatacji 30 czerwca 2009 r.
Wikipedia gives 30 June; wnp.pl and PAP of 29 June 2009 date the handover protocol to 27 June, and the record follows them.
Construction start12 maja 2006 wmurowano akt erekcyjny i poświęcono plac budowy nowego bloku
InvestorW dniu 20 stycznia 2020 TAURON Wytwarzanie S.A. poinformował, że dostosował kosztem 120 mln zł blok 460 MWe do wytwarzania ciepła grzewczego dla Zagłębia Dąbrowskiego
- money.pl / PAP29 Jun 2009InvestorFundingUtilisationStatusStageDelivery
Investornależącej do Południowego Koncernu Energetycznego Elektrowni Łagisza w Będzinie
FundingInwestycja była finansowana ze środków własnych PKE, pożyczek funduszy ekologicznych oraz ze środków pochodzących z emisji obligacji.
UtilisationO pomyślnym zakończeniu trwającego 720 godzin ruchu próbnego i formalnym przekazaniu nowego bloku do eksploatacji poinformował w poniedziałek Dariusz Wójcik z PKE. Podpisanie stosownego protokołu oznacza, że blok o mocy 460 megawatów może w pełni służyć produkcji prądu.
Status · Stage · DeliveryO pomyślnym zakończeniu trwającego 720 godzin ruchu próbnego i formalnym przekazaniu nowego bloku do eksploatacji poinformował w poniedziałek Dariusz Wójcik z PKE.
- netTG.plCostBudget
Cost · Budgetbudowę zamknięto poniżej planowanego budżetu, kosztem ok. 1,9 mld zł
- WNP.PL (Wirtualny Nowy Przemysł) – portal gospodarczy29 Jun 2009StatusStageDelivery
Status · Stage · DeliveryW należącej do Południowego Koncernu Energetycznego Elektrowni Łagisza 27 czerwca podpisano protokół przekazania do eksploatacji bloku 460 MW.
year taken from the source's publication date (29 Jun 2009)