Kormoran II-class Mine Countermeasure Vessels (Project 258): Phase I (Prototype ORP Kormoran)

completedstage: operationaldelivered
PLN 1.2 billion
contract value · data from 2013net or gross: not recorded≈ PLN 1.2 billion (value-by-stage, est., nominal)funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Kormoran II (Project 258) is a series of Polish mine countermeasure vessels built for the Polish Navy, the first new mine warfare ship for the Navy since the 1990s. A contract for the construction of three Kormoran II-class vessels, including the prototype ORP Kormoran, was signed on 23 September 2013 between the Armament Inspectorate and a Polish consortium led by the Gdańsk shipyard Remontowa Shipbuilding S.A., with the Naval Shipyard S.A. (Stocznia Marynarki Wojennej) and the Research and Development Centre Centrum Techniki Morskiej as members; the order was worth about PLN 1.2 billion. The vessels' hulls were built of non-magnetic steel. The prototype ORP Kormoran was built at the Remontowa Shipbuilding yard in Gdańsk: the keel was laid on 23 September 2014, the launch took place on 4 September 2015, and the vessel entered service (flag-raising) on 28 November 2017. This record covers Phase I of the programme, that is, procurement of the prototype under the 2013 contract; subsequent series vessels were ordered in later years under separate contracts.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[3]

Timeline

  1. Construction start23 Sep 2013
  2. Delivery28 Nov 2017

Change history

  • 28 Nov 2017stage: operational
  • 23 Sep 2014stage: construction

Significance

ORP Kormoran was the first new mine countermeasure vessel built for the Polish Navy since the 1990s and the first vessel of the new-generation Project 258 mine warfare ships. The programme confirmed domestic competence in building naval vessels with non-magnetic-steel hulls and marked the start of the rebuilding of the mine countermeasure fleet; further series vessels of the Kormoran II class were ordered based on the prototype.

Sources 4 · 3 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. DziennikZbrojny.pl
    CostConstruction startInvestorFunding
    CostWartość zlecenia na budowę trzech okrętów projektu 258 Kormoran II sięga 1,2 mld PLN.
    Construction startumowa na budowę prototypowego niszczyciela min projektu 258 Kormoran II została oficjalnie podpisana na terenie Portu Wojennego w Gdyni-Oksywiu. Do tego podniosłego wydarzenia doszło 23 września 2013 roku
    InvestorPorozumienie zostało formalnie zawarte między Inspektoratem Uzbrojenia a polskim konsorcjum, na czele którego stanęła stocznia Remontowa Shipbuilding z Gdańska
    FundingPorozumienie zostało formalnie zawarte między Inspektoratem Uzbrojenia a polskim konsorcjum, na czele którego stanęła stocznia Remontowa Shipbuilding z Gdańska wraz ze Stocznią Marynarki Wojennej S.A. oraz Ośrodkiem Badawczo-Rozwojowym Centrum Techniki Morskiej.
  2. Wikipedia (pl)
  3. Historia.org.pl8 Oct 2022
    StatusStageDelivery
    Status · Stage · DeliveryWejście do służby ORP „Kormoran” 601 23 września 2014 4 września 2015 28 listopada 2017
  4. Rzeczpospolita2013