🎭Culturestrategic

International Congress Centre in Katowice

completedstage: operationaldelivereddelayed
PLN 378 million
EU-eligible cost · data from 2015net or gross: not recorded≈ PLN 378 million (value-by-stage, est., nominal)funding: EU funds, local government, multilateral development bankLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The International Congress Centre (MCK) in Katowice is a congress and exhibition venue built next to the Spodek arena, on the site of the former 'Katowice' Hard Coal Mine, in the post-industrial Culture Zone (Strefa Kultury) adjoining the seat of the NOSPR (Polish National Radio Symphony Orchestra) and the Silesian Museum. The investor was the City of Katowice, and the design chosen for construction was developed by the Warsaw studio JEMS Architekci; the general contractor was a consortium of Warbud and Mercury Engineering. The contract with the contractor was signed on 3 October 2011, and construction began that same month; on 23 March 2015 the City of Katowice took over the building from the contractor. The first event held at the new congress centre was the Intel Extreme Masters esports tournament, which began on 12 March 2015. The cost of construction, co-financed with European Union funds, came to almost PLN 378 million, of which about PLN 196 million came from the City of Katowice's budget; in June 2011 the city took out a loan of PLN 254.2 million from the European Investment Bank, earmarked partly for this investment among others. The building's total floor area is about 38,000 m², and its main component is a multi-purpose hall able to seat around 8,000 people. In December 2018, the MCK, together with Spodek, was the main venue of the United Nations Climate Change Conference COP24.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduledelayed[1]
Utilisationin use[4]

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

Timeline

  1. Construction startOct 2011
  2. Delivery2015

Change history

  • Mar 2015stage: operational
  • Oct 2011stage: construction

Significance

The International Congress Centre is one of the largest congress and exhibition investments completed in Katowice since 1990 and forms part of the post-industrial Culture Zone on the site of the former 'Katowice' Hard Coal Mine, alongside the seat of the NOSPR and the Silesian Museum. The building gave the Upper Silesian agglomeration a large conference and trade-fair space and became part of the transformation of central Katowice from former mining land into public space. In December 2018, together with Spodek, it served as the main venue of the United Nations Climate Change Conference COP24, which was attended by more than 20,000 people from nearly 200 countries.

Sources 5 · 4 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. Wikipedia (pl)
    StatusStageCostConstruction startDeliveryInvestorFundingSchedule
    Status · Delivery23 marca tego samego roku miasto Katowice przejęło gmach od wykonawcy
    Stage · DeliveryPierwszym wydarzeniem zorganizowanym w nowym centrum kongresowym był turniej esportowy Intel Extreme Masters, który rozpoczął się 12 marca 2015 roku
    CostKoszt budowy obiektu, współfinansowany ze środków Unii Europejskiej, wyniósł blisko 378 mln zł
    Construction startUmowa z wykonawcą została podpisana 3 października 2011 roku[14] i jeszcze tego samego miesiąca rozpoczęła się budowa obiektu
    InvestorInwestor Miasto Katowice
    FundingKoszt budowy obiektu, współfinansowany ze środków Unii Europejskiej, wyniósł blisko 378 mln zł, z czego wkład własny miasta Katowice wyniósł blisko 196 mln złotych
    FundingW czerwcu 2011 roku na poczet m.in. budowy Międzynarodowego Centrum Kongresowego w Katowicach miasto zaciągnęło pożyczkę o wartości 254,2 mln zł z Europejskiego Banku Inwestycyjnego
    ScheduleWe wrześniu 2012 roku z uwagi na opóźnienia w realizacji zadania miasto Katowice rozwiązało umowę z dotychczasowym wykonawcą.
  2. Miasto Katowice
  3. Międzynarodowe Centrum Kongresowe w Katowicach
  4. PortalSamorzadowy.pl2018
    Utilisation
    UtilisationPonad 21 tysięcy osób z prawie 200 krajów członkowskich ONZ zgromadziła odbywająca się w dniach 2-16 grudnia 2018 r. w Międzynarodowym Centrum Kongresowym i Spodku Konferencja COP24
  5. Funding
    Fundingdofinansowanie z UE 182 030 830,08 zł