← all projects
Energystrategic

Poland–Slovakia gas interconnector

completedstage: operationaldelivereddelayedunderused
100 mln EUR
estimate · data from 2022net or gross: not recorded≈ 430 mln PLN (value-by-stage, est., nominal)funding: EU/CEF: GAZ-SYSTEM co-financing agreements – design works EUR 582.571 thousand (2015) and construction works EUR 45.327 million (2017)

A bidirectional high-pressure gas pipeline connecting the Polish transmission system at the Strachocina node in Podkarpacie with the Slovak gas compressor station at Veľké Kapušany, delivered jointly by Gaz-System and the Slovak operator Eustream. On the Polish side it is approximately 61 km long (approximately 164 km in total), and its transmission capacity is 5.7 billion m3 per year towards Poland and 4.7 billion m3 towards Slovakia. Construction began in 2018, completion of works was announced on 26 August 2022 in Strachocina, and commercial operation was made available from 12 November 2022. The investment is part of the North–South gas corridor; its cost was estimated at approximately EUR 100 million.

How it went

Assessment: provisional, as of 18 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduledelayed[1]
Utilisationidle[3]
commercial gas transmission through the interconnector (mainly Poland->Slovakia direction)
Current
praktycznie brak komercyjnego wykorzystania - wg relacji prasowych rura stoi pusta; stan potwierdzony w lipcu 2026 r. (gazociag 'nadal nie byl uzywany') (2022-2026)
Capacity or target
5,7 mld m3/rok w kierunku Polski oraz 4,7 mld m3/rok w kierunku Slowacji
Unit
bn m3/yr

Timeline

Slip: about 1 year vs. the original date (given as a year)

  1. Construction startSep 2018
  2. Original date2021
  3. Last stated dateOct 2022
  4. Delivery26 Aug 2022

Change history

  • 12 Nov 2022stage: operational
  • Sep 2018stage: construction

Significance

The interconnector completes the southern section of the North–South gas corridor and increases the possibilities for cross-border gas transmission between Poland and Slovakia, strengthening supply diversification in the region. In the first years after commissioning, however, its commercial use remained low – according to press reports from the end of 2025 and from July 2026, the connection was in practice not being used, because the Slovak market maintained gas supplies from other directions (including Russian gas via Turkish Stream, and ultimately an Azerbaijani contract from 2027).

Sources 8 · 5 independent · 4 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GAZ-SYSTEM S.A.26 Aug 2022
    StatusCurrent dateDeliveryFundingSchedule
    Status · Delivery · Schedule26 sierpnia br. w Strachocinie odbyła się uroczystość zakończenia budowy nowego połączenia gazowego Polski i Słowacji.
    Current datePlanowany termin uruchomienia eksploatacji komercyjnej tego interkonektora to październik 2022 roku.
    FundingNajważniejsze umowy o dofinansowanie projektu zostały podpisane przez GAZ-SYSTEM w ramach Connecting Europe Facility z unijną Agencją Wykonawczą ds. Klimatu, Innowacji i Sieci (CINEA) w 2015 r. na prace projektowe na kwotę 582.571 tys. euro oraz w 2017 r. na prace budowlane na kwotę 45.327 mln euro
    LocationTrasa gazociągu w Polsce przechodzi przez teren trzech gmin województwa podkarpackiego: Sanok, Bukowsko i Komańcza.
  2. Bankier.pl10 Nov 2022
  3. WNP.pl6 Dec 2025
    CostSignificanceUtilisation
    CostKosztujący około 100 mln euro gazociąg nie jest wykorzystywany.
    SignificanceInterkonektor nie pracuje.
    UtilisationJednak w przypadku połączenia międzysystemowego ze Słowacją tak się nie dzieje. Interkonektor nie pracuje.
  4. Inżynieria.com17 Sep 2018
    Stage historyConstruction start
    Stage history · Construction start18 września 2018 r. o godz. 15.00 oficjalnie rozpoczęła się po stronie słowackiej budowa gazowego połączenia międzysystemowego Polska–Słowacja.
  5. Inżynieria.com26 Nov 2021
    Investor
    InvestorGaz-System może rozpocząć przygotowania do przesyłu gazu ziemnego.
  6. WNP.pl18 Sep 2018
    Original date
    Original dateInterkonektor ma być gotowy w 2021 r.
  7. WNP.pl17 Jul 2026
    Utilisation
    UtilisationMimo gotowej infrastruktury gazociąg między Polską a Słowacją nadal nie przesyła surowca.
  8. Gazeta Prawna12 Nov 2022
    StageStage history
    StageGazociąg został oficjalnie uruchomiony przez premiera Słowacji Eduarda Hegera i polskiego szefa rządu Mateusza Morawieckim pod koniec sierpnia br. w Strachocinie.
    Stage historyGazowy łącznik Polska-Słowacja od soboty w pełni funkcjonalny