Improvement of Water Quality in Szczecin (Pomorzany and Zdroje Treatment Plants, ISPA/Cohesion Fund)

completedstage: operationaldelayed
PLN 1.1 billion
programme budget (multi-year) · data from 2002net or gross: not recorded≈ PLN 1.1 billion (value-by-stage, est., nominal)funding: EU funds, state special fund, the investor’s own fundsThe source gives EUR 288 million. The zloty figure is our conversion at the rate for 2002, so the site fixed rate will not reproduce it.Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The programme 'Improvement of Water Quality in Szczecin' was a multi-year water and wastewater management undertaking, carried out to bring the Szczecin agglomeration into line with European Union requirements on wastewater treatment. The undertaking began with the signing, on 18 December 2000, of the Financing Memorandum for phase I of the project (the pre-accession ISPA fund). After the signing, on 28 December 2002, of an amendment to the Financing Memorandum for phase II, ZWiK Sp. z o.o. in Szczecin became the new Beneficiary for the whole programme covering phases I and II, and the project value was set at EUR 288 million. Once all contracts had been awarded, the project value stood at EUR 262.3 million, later revised to EUR 282.2 million; following a European Commission decision, the Cohesion Fund's share of financing was raised from 80% to 90% of the value. The key elements of scope were: construction of the mechanical-biological Pomorzany Wastewater Treatment Plant together with sludge management (contract value EUR 46.9 million, designed throughput of 66,000 m³/day, 420,000 population equivalent), and the modernisation and expansion, by adding a biological stage, of the mechanical-chemical Zdroje Wastewater Treatment Plant. Technological start-up of the Pomorzany plant took place on 21 August 2009, and the whole programme was completed by the deadline of 31 December 2010.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, 2 have an assessment with no confirmed quote. How to read this section

Scheduledelayed[4]

Timeline

  1. Announced2000
  2. Construction start18 Dec 2000
  3. Last stated date31 Dec 2010

Significance

Completion of the programme gave Szczecin biological wastewater treatment, including the new mechanical-biological Pomorzany Wastewater Treatment Plant serving the left-bank part of the city, and a modernised and expanded (with an added biological stage) Zdroje Wastewater Treatment Plant. The Pomorzany plant was described as one of the largest investments of its kind in Central Europe. The undertaking was one of the largest water and wastewater management projects in Poland co-financed from the pre-accession ISPA fund and the Cohesion Fund, carried out as part of the country's alignment with EU requirements on municipal wastewater treatment.

Sources 4 · 3 independent · 2 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Zakład Wodociągów i Kanalizacji Sp. z o.o. w Szczecinie
    StatusStageCostAnnouncedConstruction startLast stated dateInvestorFunding
    Status31.12.2009 r. - zakończenie realizacji kontraktu "Budowa mechaniczno-biologicznej oczyszczalni ścieków Pomorzany wraz z gospodarką osadową"
    Stage21.08.2009 r. – nastąpił rozruch technologiczny oczyszczalni ścieków „Pomorzany”.
    Costnowym Beneficjentem całego programu na I i II fazę zostaje ZWiK Sp. z o.o w Szczecinie – wartość projektu 288 mln EUR
    Announced · Construction start18.12.2000 r. - podpisanie Memorandum Finansowego na I fazę projektu
    Last stated datedata zakończenia realizacji programu - 31.12.2010 r.
    Investornowym Beneficjentem całego programu na I i II fazę zostaje ZWiK Sp. z o.o w Szczecinie
    FundingGłównymi Funduszami, z których pochodziły środki na inwestycje były Fundusz Spójności i Europejski Fundusz Rozwoju Regionalnego.
  2. Portal Komunalny2009
  3. Urząd Miasta Szczecin – Inwestycje
  4. FundingSchedule
    FundingKoszty wszystkich inwestycji wyniosły ostatecznie 280,82 mln euro, z czego 66% czyli kwotę 185,34 mln € pokryła Unia Europejska.
    FundingPozostałą kwotę ok. 95,5 mln € zapewniono dzięki preferencyjnym pożyczkom i kredytom z konsorcjum finansowego, w skład którego weszły Bank Ochrony Środowiska oraz Narodowy i Wojewódzki Fundusz Ochrony Środowiska i Gospodarki Wodnej.
    FundingCzęść pieniędzy stanowił również wkład własny Zakładu Wodociągów i Kanalizacji Sp. z o. o. w Szczecinie.
    ScheduleGłównie te obiektywne czynniki sprawiły, że po uzgodnieniach z instytucjami nadzorującymi program, planowane pierwotnie na grudzień 2007 zakończenie kontraktu przesunięte zostało o dwa lata.