HTGR-POLA – high-temperature research reactor (NCBJ, Świerk)

plannedstage: announced
PLN 1.5 billion
estimate · data from 2 Apr 2025net or gross: not recorded≈ PLN 1.5 billion (value-by-stage, est., nominal)funding: state fundsLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A project for a Polish research and demonstration high-temperature helium-cooled reactor with a thermal power of 30 MW, developed at the National Centre for Nuclear Research in Świerk together with Japan's JAEA. The basic design is complete, and work on it began in 2021 with a Ministry of Science grant. At a Sejm committee sitting on 2 April 2025 NCBJ estimated the construction cost at no less than PLN 1.5 billion and the detailed engineering design at a minimum of PLN 100–140 million. The sources record no decision on funding the next stages.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Significance

According to NCBJ the reactor is to become the basis for commercial reactors for Polish industry that would supply process steam. The design team states that the fifteen largest Polish chemical plants need at least 6.5 GW of thermal power in the form of steam. Further stages depend on a funding decision, and the Ministry of Industry representative at the committee took no clear position on it.

Sources 3 · 3 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Sejm Rzeczypospolitej Polskiej2 Apr 2025
    StatusCost
    StatusW tej chwili wykonanie projektu technicznego szacujemy na kwotę 100–140 mln zł minimum
    Costoszacowaliśmy w tamtym czasie na ok. 1,5 mld zł
  2. Narodowe Centrum Badań Jądrowych23 Sep 2024
    StageInvestor
    StageThe project is currently at a high level of technological readiness, including the basic design with a significant part of the so-called Preliminary Safety Report (PSR) necessary for its licensing and further design work, commencement of construction and commisioning.
    InvestorA team of experts from the National Centre for Nuclear Research, based on the experience of the MARIA research reactor operating in Świerk for 50 years
  3. World Nuclear News20 Jun 2023
    Funding
    FundingFunding for the project between 2021 and 2024 totals PLN60 million