Harmony Link (Poland–Lithuania electricity interconnection)
The second cross-border electricity interconnection between Poland and Lithuania, delivered jointly by the transmission system operators PSE and Litgrid. Originally approved in May 2021 as a 700 MW submarine HVDC cable (cost approx. EUR 700 million with a CEF grant of over EUR 500 million, completion planned for 2025). The tenders for the offshore variant were cancelled in April 2023 due to a sharp rise in costs, and in late 2023 the operators agreed on an onshore variant. In its current form, on the Polish side an underground 220 kV cable line, Ełk Bis–Polish border, approx. 100 km long, is being built, running through six communes in the Warmińsko-Mazurskie and Podlaskie Voivodeships, together with two new substations — Norki in the Kalinowo commune and Wigry in the Suwałki commune — and modernization of the existing 220 kV Ostrołęka–Ełk Bis line; on the Lithuanian side the connection reaches the new Gižai substation. Construction is planned for 2026–2030, with the connection to be commissioned by the end of 2030.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
Slip: +60 mo. vs. the original date
- Announced 21 Dec 2018
- Original date 2025
- Current date 2030
Change history
- Aug 2024 stage: permits
- 21 Dec 2018 stage: announced
Significance
A key element of synchronizing the Baltic states' power systems with the continental European grid and the second cross-border connection between Poland and Lithuania. It will increase energy exchange capacity and security of supply in the region; on the Polish side it means expansion of the transmission grid in Masuria and the Suwałki region (new Norki and Wigry substations, modernization of the Ostrołęka–Ełk Bis line).
Sources 9 · 7 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Polskie Sieci Elektroenergetyczne 31 May 2021CostOriginal date
Cost „Całkowity koszt Harmony Link wynosi 700 milionów euro."
Original date „Przewidywany termin ukończenia prac to 2025 rok."
- PSE and Litgrid signed cooperation agreement to build Harmony Link interconnector as overland line ↗ archived ✓Polskie Sieci Elektroenergetyczne 15 Jul 2024InvestorCurrent dateStatus
Investor „PSE and Litgrid, transmission system operators in Poland and Lithuania"
- Polskie Sieci Elektroenergetyczne (inwestycje.pse.pl)StatusCurrent date
Status „przetargi na prace budowlane zostaną przeprowadzone w 2026 r."
Current date „nowe połączenie zostanie oddane do użytku do końca 2030 r."
- BalticWind.EU 19 Aug 2024Stage
Stage „started spatial planning and environmental impact assessment works in Lithuania"
Stage history „Litgrid "started spatial planning and environmental impact assessment works in Lithuania" for the project."
- BiznesAlert.pl 15 Nov 2023Status
- PortalMorski.pl 21 Dec 2023Status
- Wikipedia (EN)Announced
Announced „On 21 December 2018, Lithuanian electricity grid operator Litgrid and Polish electricity grid operator PSE signed an agreement in order to start planning the cable."
- investmap.pl 9 Feb 2026
locations „Inwestycja obejmie sześć gmin w województwach warmińsko‑mazurskim i podlaskim"
- wnp.pl 29 Jan 2026