A planned gas pipeline, Skanled, from Norwegian fields to customers in Norway, Sweden and Denmark. PGNiG held a 15 per cent stake in the consortium and had booked transmission capacity to send gas to Denmark and on to Poland through Baltic Pipe. The construction cost was estimated at about PLN 5.4 billion. In April 2009 the consortium suspended the investment indefinitely.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section
Significance
For Poland the project was meant to open access to gas from the north, beyond Russian supplies. The consortium suspended the investment indefinitely. Offshore Magazine judged that the delay could hasten construction of the LNG terminal in Świnoujście.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Parkiet10 Apr 2009StageCost
StageJego zatwierdzenie będzie podstawą do rozpoczęcia budowy Skanledu
Costktórej koszty szacowane są na około 5,4 mld zł
- Inżynier Budownictwa30 Apr 2009StatusInvestor
StatusKonsorcjum firm, które miało wybudować gazociąg dostarczający do Polski gaz z Norwegii, zawiesiło bezterminowo inwestycję.
InvestorDla Polskiego Górnictwa Naftowego i Gazownictwa to bardzo zła informacja, gdyż ma ono 15% udziałów w przedsięwzięciu.
- Offshore Magazine11 May 2009StatusSignificance
StatusThe recent postponement of the $1.5 billion Skanled pipeline project is likely to have a direct impact on future gas supply to Scandinavia.
SignificanceFor Poland, the delay in Skanled may hasten its efforts to bring forward the construction of an LNG terminal at Świnoujście