A national transmission gas pipeline approximately 308 km long, with a diameter of 1000 mm and a maximum operating pressure of 8.4 MPa, built by GAZ-SYSTEM and connecting the gas compressor station in Gustorzyn with the compressor station in Wronów. The investment was carried out in three stages: Gustorzyn–Leśniewice (54 km), Leśniewice–Rawa Mazowiecka (100 km) and Rawa Mazowiecka–Wronów (154 km), with its route running through four voivodeships: Kujawsko-Pomorskie, Mazowieckie, Łódzkie and Lubelskie. Construction works began in early 2022, and the official completion of construction took place on 4 October 2023; the handover of the entire pipeline for operation was scheduled for the end of 2023. The project received more than PLN 700 million in EU funding from the Operational Programme Infrastructure and Environment as well as REACT-EU support.
How it went
Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
- Announced2021
- Construction start2022
- Delivery4 Oct 2023
Change history
- 4 Oct 2023stage: commissioning
- 2022stage: construction
Significance
The pipeline connects the gas compressor stations in Gustorzyn and Wronów over approximately 308 km, running through four voivodeships (Kujawsko-Pomorskie, Mazowieckie, Łódzkie and Lubelskie). It increases access for central and eastern Poland to a stable source of gas, raises the flexibility of the national transmission system and enables the connection of further customers to the GAZ-SYSTEM network, forming part of the expansion of transmission infrastructure in the central part of the country.
Sources 7 · 4 independent · 2 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- GAZ-SYSTEM S.A.4 Oct 2023AnnouncedDelivery
AnnouncedInwestycja rozpoczęła się w 2021 r.
LocationGazociąg Gustorzyn – Wronów o długości 308 km łączy tłocznię gazu w Gustorzynie z tłocznią we Wronowie.
DeliveryGAZ-SYSTEM zakończył budowę gazociągu Gustorzyn – Wronów o długości 308 km.
- NBI (Nowoczesne Budownictwo Inżynieryjne)Oct 2023StatusStageConstruction startDelivery
Status · Stage · DeliveryOficjalne zakończenie budowy odbyło się 4 października 2023 r. na terenie Terenowej Jednostki Eksploatacji Wronów.
Construction startPrace budowlane rozpoczęły się z początkiem 2022 r.
LocationJej trasa przebiega przez cztery województwa: kujawsko-pomorskie, mazowieckie, łódzkie i lubelskie.
GeometryGazociąg Gustorzyn – Wronów o długości 308 km łączy tłocznię gazu w Gustorzynie z tłocznią we Wronowie.
- Ministerstwo Funduszy i Polityki Regionalnej2023
- Mapa Dotacji UE / Ministerstwo Funduszy i Polityki RegionalnejInvestor
InvestorOPERATOR GAZOCIĄGÓW PRZESYŁOWYCH GAZ-SYSTEM S.A.
- Mapa Dotacji UE / Ministerstwo Funduszy i Polityki Regionalnej
- Ministerstwo Funduszy i Polityki Regionalnej (POIiŚ)2023Funding
FundingInwestycja otrzymała 712,9 mln zł dofinansowania z Programu Infrastruktura i Środowisko.