⚡Energystrategic

GAZ-SYSTEM 2009–2015 investment programme (trunk pipelines of the North–South Gas Corridor)

completedstage: operationaldelivered
PLN 3.8 billion
programme budget (multi-year) · data from 2015net or gross: not recorded≈ PLN 3.8 billion (value-by-stage, est., nominal)funding: EU funds, multilateral development bank, private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A multi-year programme to expand the national gas transmission system, carried out by the transmission system operator GAZ-SYSTEM S.A. between 2009 and 2015. It built more than 1,200 kilometres of new high-pressure gas pipelines, 2 compressor stations and 41 gas stations, mainly in north-western and central Poland. The network included trunk pipelines on the Świnoujście–Szczecin, Szczecin–Gdańsk, Szczecin–Lwówek, Gustorzyn–Odolanów and Rembelszczyzna–Gustorzyn routes, forming the Polish section of the EU-supported North–South Gas Corridor and bringing gas from the LNG terminal then being built in Świnoujście into the national system. The investment programme was worth more than PLN 3.8 billion, of which about PLN 1.2 billion was European Union co-financing. The programme's summary coincided with the opening of one of the key pipelines on 5 October 2015.

How it went

Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]

Timeline

  1. Announced2009
  2. Construction start2009
  3. Delivery2015

Significance

The 2009–2015 programme substantially expanded the national gas transmission system (more than 1,200 km of new pipelines, 2 compressor stations and 41 gas stations) and created the Polish section of the EU-supported North–South Gas Corridor. Trunk pipelines such as Świnoujście–Szczecin and Szczecin–Lwówek enabled gas from the LNG terminal in Świnoujście to be received and carried further into the country, reducing dependence on supplies from a single direction and strengthening Poland's energy security and integration with the European transmission system.

Sources 7 · 4 independent · 4 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GAZ-SYSTEM S.A.Oct 2015
    StatusStageCostConstruction startAnnouncedDeliveryInvestorFunding
    Status · Announced · Investor · DeliveryPonad 1200 kilometrów nowych gazociągów, 2 tłocznie gazu oraz 41 stacji gazowych to bilans sześcioletniego programu inwestycyjnego zrealizowanego przez Operatora Gazociągów Przesyłowych GAZ-SYSTEM S.A.
    Stage · DeliveryW ramach podsumowania programu inwestycyjnego w dniu 5 października 2015 r. odbyło się otwarcie jednego z kluczowych gazociągów
    Cost · Construction startW latach 2009-2015 GAZ-SYSTEM S.A. wydał na realizację zadań w systemie przesyłowym kwotę ponad 3,8 mld złotych.
    FundingProjekty GAZ-SYSTEM S.A. wspolfinansowane byly z trzech programow unijnych, a najwieksza kwota dofinansowania - lacznie ok. 1 mld zlotych - pochodzila z Programu Infrastruktura i Srodowisko 2007-2013.
    FundingW finansowaniu inwestycji istotne znaczenie miały również kredyty pozyskane z banków komercyjnych i europejskich instytucji finansowych, takich jak Europejski Bank Inwestycyjny czy Europejski Bank Odbudowy i Rozwoju.
  2. money.pl27 Nov 2014
  3. Wikipedia (pl)
  4. Funding
    Fundingrealizacja projektu jest dofinansowania 50 mln euro ze środków z unijnego programu "European Energy Programme for Recovery" (EEPR).
  5. Najwyższa Izba Kontroli (NIK), Departament Gospodarki, Skarbu Państwa i Prywatyzacji4 Nov 2013
  6. Pipeline Technology Journal (ptj)23 Oct 2015
    Investor
    InvestorIn addition to the new gas pipelines, GAZ-SYSTEM has also built two compressor stations and 41 gas stations, which provides new opportunities for developing the domestic gas network, enables its liberalization and increases Poland's energy security. GAZ-SYSTEM S.A., the operator of gas transmission pipelines in Poland, will complete the development of the ambitious project by the end of 2015.