Miecznik Frigates (Arrowhead 140 type) — PGZ Stocznia Wojenna Gdynia
A programme to build in Poland three modern multi-role frigates of project 106 (codename Miecznik) for the Polish Navy, based on the British Arrowhead 140 design by Babcock International. The ships — the future ORP Wicher, ORP Burza and ORP Huragan — are being built at the Gdynia-based PGZ Stocznia Wojenna, the technical leader of the PGZ-MIECZNIK consortium. Each vessel is approximately 138 m long with a maximum displacement of approximately 7,000 t. The construction also involved the largest investment programme in the shipyard's more than one-hundred-year history in halls, machinery and equipment. As of July 2026, all three frigates are under construction: the hull of the first (Wicher) is in advanced assembly, and work has already begun on the last (Huragan).
Timeline
- Announced 27 Jul 2021
- Construction start 31 Jan 2024
- Current date 2031
Change history
- 28 Apr 2026 stage: construction
- 31 Jan 2024 status: under construction Keel-laying of the first frigate (the future ORP Wicher) at PGZ Stocznia Wojenna in Gdynia.
- 31 Jan 2024 stage: construction
- 27 Jul 2021 stage: announced
Significance
Miecznik is the most important post-war combat shipbuilding programme in Poland — three multi-role frigates are to replace worn-out vessels and become the backbone of the Polish Navy's combat capabilities in the Baltic. Building the vessels at the Gdynia-based PGZ Stocznia Wojenna, together with the transfer of technology from Babcock International and the largest investment programme in the shipyard's history, rebuilds national competencies in the design and production of large surface ships and maintains jobs in the Polish shipbuilding and armaments industry.
Sources 6
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- PGZ Stocznia WojennaInvestorowner.typekindDescription
- Naval News 29 Apr 2026StatusStageStage historyCurrent date
Status „Construction of the first frigate – Wicher – is at an advanced stage of hull assembly."
Stage „The ceremony took place on 28 April 2026 at the PGZ Stocznia Wojenna in Gdynia – the technical leader of the PGZ-MIECZNIK Consortium."
Stage history „With the start of construction on the Huragan, we are entering the next phase of the "Miecznik" programme."
Current date „Completion of the "Miecznik" programme, i.e. the delivery of the third vessel – Huragan – to the Polish Navy, is scheduled for the end of 2031."
- Polska Agencja Prasowa 2025Costcost.basisStatus
Cost „Wartość umowy wynosiła początkowo ok. 8 mld zł, niemniej w wyniku zawartych aneksów wzrosła pod koniec 2023 roku do ok. 15 mld zł."
- PGZ Stocznia WojennaCost
cost.basis „the contract, the value of which after signing all the annexes to date amounts to approximately PLN 14.8 billion"
- Naval News Feb 2024Construction startStatus history
Construction start „On January 31, a keel laying ceremony of the future ORP Wicher was held at PGZ Stocznia Wojenna (PGZ Naval Shipyard) in Gdynia."
- ZBiAMAnnouncedStage history
Announced „umowy nr IU/42/XI-49/ZW/NEG/ROZ/DOS/Z/2021/332 podpisanej 27 lipca 2021 r."