Zwartowo Photovoltaic Farm (204 MWp)

completedstage: operationaldelivered
EUR 200 million
estimate · data from 2022net or gross: not recorded≈ PLN 860 million (value-by-stage, est., nominal)funding: multilateral development bank, private financeLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Poland's largest photovoltaic farm, located in the village of Zwartowo in the Choczewo commune (Wejherowo County, Pomorskie Voivodeship), covering an area of about 300 ha. The first stage, with a capacity of 204 MWp, was built by the Polish company Respect Energy in cooperation with the German firm Goldbeck Solar and was officially opened at the end of September 2022. The estimated value of the investment is approximately EUR 200 million; financing was provided by a consortium of three banks (Pekao, PKO BP and EBRD). A further expansion of the complex to approximately 285–290 MWp is planned, and a separate Zwartowo III project envisages the construction of another farm with a capacity of 255 MWp together with an energy storage facility with a capacity of 184 MW, for which the company secured more than PLN 326 million in preferential financing from the National Recovery Plan (KPO).

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverydelivered[2]
Utilisationin use[4]
operational, grid-connected PV farm; the first large-scale PV source in Poland admitted to provide balancing services for PSE
Current
obecnie druga największa elektrownia PV w Polsce, czynna od IX 2022 (2026-05)
Capacity or target
204 MWp / ok. 230 GWh rocznie (prognoza)

Timeline

  1. DeliverySep 2022

Change history

  • 29 Sep 2022stage: operational

Significance

Following completion of the first stage (204 MWp), the installation became the largest photovoltaic farm in Poland and one of the largest in Central and Eastern Europe. Ultimately it is to supply green energy to approximately 153 thousand households, generating around 230 GWh of energy annually. The subsequent expansion stages and the Zwartowo III project with its large-scale energy storage facility are intended to further increase the share of renewable energy sources in the power system in the Pomorskie region.

Sources 4 · 4 independent · 3 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. RynekElektryczny.pl
    CostFunding
    CostWartość elektrowni wynosi około 200 mln euro.
    FundingProjekt farmy fotowoltaicznej Zwartowo finansowany jest przez konsorcjum trzech banków: Banku Pekao SA, PKO BP oraz Europejskiego Banku Odbudowy i Rozwoju (EBOR).
  2. MuratorPlus.pl
    StatusDeliveryInvestorSignificance
    Status · DeliveryPierwszy etap budowy farmy fotowoltaicznej w Zwartowie został zakończony pod koniec września 2022 roku.
    InvestorZostała wybudowana przez polską spółkę Respect Energy
    LocationFarma fotowoltaiczna znajduje się w woj. Pomorskim w miejscowości Zwartowo na terenie gminy Choczewo w powiecie wejherowskim.
    SignificanceMoc farmy fotowoltaicznej wynosi 204 MWp
  3. Respect Energy29 Sep 2022
    StageSignificance
    StageOficjalne otwarcie farmy Zwartowo – zlokalizowanej w województwie pomorskim – zakończyło pierwszy etap budowy największej inwestycji fotowoltaicznej w Polsce
    SignificanceFarma zlokalizowana na powierzchni 300 ha docelowo dostarczy zieloną energię do około 153 tys. gospodarstw domowych.
  4. Gramwzielone.pl27 May 2026
    DescriptionUtilisation
    DescriptionProjekt Zwartowo III zakłada budowę jednej z największych w kraju farm fotowoltaicznych, o mocy 255 MWp, a także wielkoskalowego magazynu energii o mocy 184 MW.
    UtilisationBędąca obecnie drugą największą polską elektrownią fotowoltaiczną PV Zwartowo niedawno stała się pierwszym wielkoskalowym źródłem PV dopuszczonym do świadczenia usług bilansujących