Rożnów II Pumped-Storage Power Plant

plannedstage: permits
PLN 6.8 billion
estimate · data from Jul 2026net or gross: not recorded≈ PLN 6.8 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of the Rożnów II pumped-storage power plant on Lake Rożnów, adjacent to the existing Rożnów Hydroelectric Power Plant, in the Łososina Dolna municipality in Nowy Sącz County (Małopolskie Voivodeship). The investor is TAURON Polska Energia. In the baseline variant the plant is to reach a capacity of approx. 767 MW and approx. 3.1 GWh of storage capacity (usable volume of the upper reservoir 7.7 million m³, with an option to increase it to 11.5 million m³), which would make it one of the largest energy storage facilities in Poland – alongside PGE's planned Młoty pumped-storage plant (1,050 MW / approx. 4.1 GWh). Lake Rożnów is to serve as the lower reservoir, and the upper reservoir is to be built on elevations on the southern shore of the lake; approx. 70-80% of the land required for the investment is covered by lease agreements. The estimated cost of the investment is approx. PLN 6.8 billion (media report approx. PLN 7 billion). The project was announced publicly in October 2024, together with the completion of the first stage of preparatory works (preliminary feasibility study, securing of land, grid connection application). At the end of November 2025 the project obtained grid connection conditions from the TSO PSE (800 MW connection capacity), and the process of obtaining an environmental decision was started. On 13 July 2026 the Ministry of Energy and TAURON signed a letter of intent on supporting the construction of pumped-storage plants; the investment decision is planned for 2028, conditional on a support scheme being in place, with delivery in 2028-2033.

How it went

Assessment: too early to assess, as of 25 Aug 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet. How to read this section

Deliverynot yet due[2]
Schedulenot yet due[7]

Timeline

  1. AnnouncedOct 2024
  2. Original date2033

Change history

  • Dec 2025stage: permits
  • Oct 2024stage: announced

Significance

Rożnów II is intended to be one of the largest energy storage facilities in Poland (approx. 767 MW / 3.1 GWh, approx. 4 hours of operation in generation mode) and one of the elements stabilising the national power system as the share of renewables grows. The upper reservoir is also to serve a flood-protection function – according to the investor it will be able to absorb up to 10% of the inflow of a Dunajec flood wave into Lake Rożnów. Delivery depends on a support model for pumped-storage plants being worked out (the July 2026 letter of intent between the Ministry of Energy and TAURON, requiring among others European Commission approval of the support scheme) and on the investment decision planned for 2028; it is to be followed by an approx. one-year general-contractor tender and approx. 5 years of construction.

Sources 8 · 7 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Energii (gov.pl)13 Jul 2026
    Cost
    Costszacunkowy koszt inwestycji – ok. 6,8 mld zł
  2. TAURON Polska Energia (biuro prasowe)15 Oct 2024
    AnnouncedOriginal dateDelivery
    AnnouncedTAURON zakończył pierwszy etap prac przygotowawczych Elektrowni Szczytowo-Pompowej w Rożnowie
    Original date · DeliveryGrupa TAURON planuje uzyskanie kompletu pozwoleń oraz decyzję inwestycyjną, natomiast w 2033 rozpoczęcie eksploatacji obiektu.
  3. Gramwzielone.pl31 Dec 2025
    Stage
    StageRozpoczął też proces pozyskiwania decyzji środowiskowej.
  4. Portal Komunalny12 Jan 2026
    Investor
    InvestorTauron Polska Energia SA planuje budowę nowej elektrowni szczytowo-pompowej Rożnów II
  5. Energetyka2413 Jul 2026
  6. Portal Samorządowy24 Aug 2026
  7. WNP.pl
    StatusSchedule
    Status · Scheduledecyzja inwestycyjna dotycząca Rożnowa II planowana jest na 2028 r.
  8. StockWatch.pl13 Jul 2026