Energystrategic

Młoty Pumped-Storage Power Plant (revival)

under construction stage: permits
5.0 bn PLN
estimate · data from Jan 2026 ≈ 5.0 bn PLN (value-by-stage, est., nominal)

The revival of the Młoty pumped-storage power plant in the Bystrzyckie Mountains, on the Bystrzyca Łomnicka river, in the village of Młoty in the Bystrzyca Kłodzka municipality in Kłodzko County (Dolnośląskie Voivodeship). Construction began in 1973 and was abandoned; the project is being taken up again by PGE Polska Grupa Energetyczna, carrying it out through the special-purpose company PGE Inwest 12, in which NFOŚiGW holds a 49% stake. Under the current assumptions, the plant is to reach a capacity of 1,050 MW and approx. 4,090 MWh of storage capacity. The estimated cost of the investment is approx. PLN 5 billion (some sources give at least PLN 6 billion). Carrying out this variant of the project requires flooding the entire village of Młoty to create the lower reservoir. At the turn of 2025 and 2026 the company submitted an environmental report to the Regional Directorate for Environmental Protection (RDOŚ) in Wrocław, and the project schedule depends on the timing of obtaining the environmental decision.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial

Timeline

  1. Original date 2030

Change history

  • Dec 2025 stage: permits
  • Jul 2024 stage: permits

Significance

The project is intended to be one of the most advanced undertakings to build a pumped-storage power plant in Poland and to serve for energy storage and stabilisation of the national power system during peaks in demand. At full capacity of 1,050 MW the installation could operate for approx. four hours. The lower reservoir on the Bystrzyca river is also to serve a retention function, reducing the risk of flooding in the area of Bystrzyca Kłodzka. The price of the undertaking, however, is the flooding of the entire village of Młoty to create the lower reservoir, which raises social opposition and environmental concerns.

Sources 5 · 5 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. AgroNews 12 Jan 2026
    CostStageStage historyStatusSignificance
    Stage history „Na dzień przed końcem roku spółka złożyła wymagany dokument"
    Cost „koszt inwestycji wyniesie ok. 5 mld zł"
  2. Gramwzielone.pl 2 Jun 2025
    InvestorStatusSignificance
    Status „Jak podaje PGE, harmonogram projektu uzależniony jest od terminu uzyskania decyzji środowiskowej."
    Investor „Fundusz został udziałowcem (49%) spółki celowej PGE Inwest 12."
  3. Forsal.pl 30 Apr 2025
    DescriptionSignificance
  4. wywlaszczenie.pl 15 Jan 2025
    Stage historySignificance
    Stage „W lipcu 2024 r. inwestor wystąpił o decyzję środowiskową"
    locations „Dolnym Śląsku w powiecie kłodzkim"
  5. Money.pl 10 Nov 2024
    Original date
    Original date „Pierwotny harmonogram przewidywał, że będzie gotowa w 2030 r."