A planned private 1,600 MW coal-fired power plant (2 x 800 MWe) in Rajkowy near Pelplin in Pomorskie Voivodeship, developed by Polenergia, a company of the Kulczyk group. The unit was to be fuelled by hard coal (on the order of 4.5-5 million tonnes per year). The investment did not materialise: following the annulment of the building permit and a June 2019 ruling of the Supreme Administrative Court in Warsaw, the project ended definitively.
The investment was not carried out. The June 2019 ruling of the Supreme Administrative Court in Warsaw marked the definitive end of the project; earlier, as far back as 2015, the investor had pointed to the absence of economic grounds for its implementation.
How it went
Assessment: settled, as of 18 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 carry no assessment yet. How to read this section
Significance
The abandonment of the largest planned private coal-fired power plant in Poland is sometimes read as the symbolic end of the era of new coal units in the country. After dropping the project, the investor redirected its activity towards renewable energy, including offshore wind farms on the Baltic Sea.
Sources 6 · 5 independent · 5 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- OKO.press27 Jun 2019StatusFailure descriptionDescription
Nameopalanej węglem Elektrowni Północ koło Pelplina
StatusDecyzja Naczelnego Sądu Administracyjnego (NSA) w Warszawie oznacza definitywny koniec Elektrowni Północ
Failure descriptionJuż w 2015 roku Polenergia informowała o braku przesłanek ekonomicznych do realizacji projektu Elektrowni Północ.
DescriptionElektrownia Północ miała mieć moc 1600 megawatów
- Dzikie Życie2019
- Dziennik.plStageInvestor
StageW marcu 2015 roku Starosta Tczewski wydał decyzję o pozwoleniu na budowę dla tej instalacji
InvestorPolenergia rozpoczęła starania na budowę elektrowni Północ w marcu 2011 roku i planowała jej zakończenie w 2020 roku.
StageW grudniu 2015 roku Wojewoda Pomorski uchylił decyzję o pozwoleniu na budowę, uznając ją za jawnie sprzeczną z prawem.
- Inwestycje Energetyczne (Politechnika Warszawska)
Locationwojewództwie pomorskim
CategoryPaliwo: Węgiel kamienny dostarczany z pobliskich kopalni Bogdanka, ok. 5 mln ton rocznie
- Global Energy Monitor
- Gazeta Prawna19 Jun 2019Delivery
DeliveryPolenergia nie będzie mogła wybudować elektrowni węglowej Północ w okolicy Pelplina