Nowy Rybnik gas-and-steam power plant (CCGT Rybnik, 882 MW)

under construction stage: construction delayed
3.0 bn PLN
contract value · 2023 prices ≈ 3.0 bn PLN (value-by-stage, est., nominal)

The Nowy Rybnik gas-and-steam unit (CCGT) with a capacity of 882 MW is a PGE investment carried out at the site of the Rybnik Power Plant by a consortium of Polimex Mostostal and Siemens Energy. The new gas unit is to replace four coal units being shut down with a combined capacity of about 900 MW. The contract for the construction of the unit, worth about PLN 3 billion net, was concluded in 2023, and the original commissioning date for the unit was set for December 2026. Due to delays, the handover of the unit was postponed to early 2027; according to reports from 2026, construction progress had reached about 85 percent.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial
Schedule delayed

Timeline

Slip: +3 mo. vs. the original date

  1. Original date Dec 2026
  2. Current date 6 Mar 2027

Significance

The investment replaces coal capacity being phased out with a low-emission gas-and-steam unit and strengthens the security of electricity supply in the Silesia region. The 882 MW unit is cited as one of the largest installations of its kind in Europe and is intended to stabilise the operation of the power system during the move away from coal.

Sources 5 · 4 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. Polimex Mostostal S.A. Feb 2023
    CostOriginal dateInvestor
    Cost „budowy bloku o wartości ok. 3 mld złotych netto"
    Original date „Oddanie bloku do eksploatacji planowane jest na grudzień 2026 roku"
    locations[0] „bloku gazowo - parowego o mocy 882 MW w Rybniku"
  2. WNP.pl 2025
    Current date
    Current date „4 sierpnia 2025 roku został podpisany aneks, który zmienia datę przekazania rybnickiego bloku do eksploatacji z 31 grudnia 2026 roku na 6 marca 2027 roku."
  3. WNP.pl 2026
    StatusStageprogress.pctCurrent date
    Status „Przekazanie bloku do eksploatacji planujemy, że nastąpi na przełomie I i II kwartału przyszłego roku"
    Stage „około 85 proc."
  4. Rynek Infrastruktury
    Cost
  5. Nasz Wodzisław
    Investor
    Investor „W Rybniku powstanie nowa elektrownia gazowa. PGE podpisało umowę z Polimex Mostostal S.A. i Siemens Energy"