Nowy Rybnik gas-and-steam power plant (CCGT Rybnik, 882 MW)
The Nowy Rybnik gas-and-steam unit (CCGT) with a capacity of 882 MW is a PGE investment carried out at the site of the Rybnik Power Plant by a consortium of Polimex Mostostal and Siemens Energy. The new gas unit is to replace four coal units being shut down with a combined capacity of about 900 MW. The contract for the construction of the unit, worth about PLN 3 billion net, was concluded in 2023, and the original commissioning date for the unit was set for December 2026. Due to delays, the handover of the unit was postponed to early 2027; according to reports from 2026, construction progress had reached about 85 percent.
How it went
Assessment: too early to assess, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
Slip: +3 mo. vs. the original date
- Original dateDec 2026
- Current date6 Mar 2027
Significance
The investment replaces coal capacity being phased out with a low-emission gas-and-steam unit and strengthens the security of electricity supply in the Silesia region. The 882 MW unit is cited as one of the largest installations of its kind in Europe and is intended to stabilise the operation of the power system during the move away from coal.
Sources 8 · 5 independent · 7 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Polimex Mostostal S.A.Feb 2023CostOriginal dateFunding
Costbudowy bloku o wartości ok. 3 mld złotych netto
Original dateOddanie bloku do eksploatacji planowane jest na grudzień 2026 roku
Locationbloku gazowo - parowego o mocy 882 MW w Rybniku
FundingRealizacja projektu zostanie częściowo sfinansowana ze środków pozyskanych z nowej emisji akcji PGE z 2022 roku
- WNP.pl2025Current dateSchedule
Current date · Schedule4 sierpnia 2025 roku został podpisany aneks, który zmienia datę przekazania rybnickiego bloku do eksploatacji z 31 grudnia 2026 roku na 6 marca 2027 roku.
- WNP.pl2026StatusStageProgress
StatusPrzekazanie bloku do eksploatacji planujemy, że nastąpi na przełomie I i II kwartału przyszłego roku
StageInwestycja jest zaawansowania w około 85 proc.
Progressokoło 85 proc.
- Rynek Infrastruktury
- [5]W Rybniku powstanie nowa elektrownia gazowa. PGE podpisało umowę z Polimex Mostostal S.A. i Siemens Energy ↗archived ✓Nasz WodzisławInvestor
InvestorW Rybniku powstanie nowa elektrownia gazowa. PGE podpisało umowę z Polimex Mostostal S.A. i Siemens Energy
- Funding
FundingPowstający blok 882 MW w Rybniku w grudniu 2022 r. uzyskał 17-letni kontrakt w aukcji głównej rynku mocy, który zacznie obowiązywać od 2027 r.