CCGT Grudziądz gas-and-steam power plant (Unit I, 563 MW)

under constructionstage: commissioning
2.0 bn PLN
estimate · data from 2025net or gross: not recorded≈ 2.0 bn PLN (value-by-stage, est., nominal)

The CCGT Grudziądz gas-and-steam unit (Unit I) with a net capacity of approx. 563 MW, built by the company CCGT Grudziądz of the Energa Group (Orlen Group). The general contractor under the EPC formula is a consortium of Metlen (formerly Mytilineos) and Siemens Energy. The value of the investment is approx. PLN 2 billion. The cornerstone was laid in May 2023, and the original commissioning date (2025) was postponed to 2026. In 2026 the unit entered the start-up phase and delivered energy to the national power grid for the first time.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Original date2025
  2. Current date2026

Change history

  • Jul 2026stage: commissioning
  • 18 May 2023stage: construction

Significance

The new unit increases the dispatchable, flexible generation capacity of the national system (operating in the range from just under 40% to 100% of capacity), supporting the balancing of the system amid a growing share of renewables and replacing high-emission coal capacity. The unit is covered by capacity-market support (a capacity obligation of 518 MW from 2026).

Sources 8 · 8 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. wGospodarce.pl18 May 2023
    Stage history
    Stage historyObecnie na terenie budowy prowadzone jest palowanie, a także zbrojenie i wylewanie płyt fundamentowych.
  2. Metlen Energy & Metals
    InvestorOriginal date
    InvestorSPV CCGT Grudziądz Sp z o.o. (owned entirely by Energa S A, part of Orlen Group)
    Original date38 months after the signing of the contract
    LocationGrudziadz, Poland
  3. CCGT Grudziądz Sp. z o.o.8 Jan 2026
  4. Inwestycje.pl13 Jul 2026
    StatusStageStage history
    Status · StagePierwszy zapłon turbiny gazowej oraz synchronizacja generatora z krajową siecią elektroenergetyczną to kluczowe etapy rozruchu bloku gazowo-parowego.
    Stage historyenergia z CCGT Grudziądz po raz pierwszy trafiła do systemu
  5. Zawsze Pomorze11 Jul 2025
    SignificanceCost
    Name563 MW netto
    Significancemogący pracować w zakresie od niespełna 40% do 100% mocy z zachowaniem wszystkich standardów emisyjnych
    CostWarty ok. 2 mld zł blok gazowo-parowy w Grudziądzu zasilany będzie wysokometanowym gazem ziemnym.
  6. WysokieNapiecie.pl2026
    Current date
    Current dateBloki CCGT w Grudziądzu i Ostrołęce ruszą w I poł. 2026, być może w I kw. 2026
  7. Funding
    FundingPKN ORLEN S.A. zobowiązał się w Porozumieniu do pokrycia do 100% nakładów inwestycyjnych związanych z realizacją Projektu, ale nie więcej niż 1,8 mld zł, pod warunkiem zawarcia przez spółkę CCGT Grudziądz Sp. z o.o. (spółka celowa realizująca Projekt) umowy mocowej.
  8. Funding
    FundingBlok ma obowiązek mocowy w wysokości 518 MW, począwszy od 2026 r.