CCGT Grudziądz gas-and-steam power plant (Unit I, 563 MW)
The CCGT Grudziądz gas-and-steam unit (Unit I) with a net capacity of approx. 563 MW, built by the company CCGT Grudziądz of the Energa Group (Orlen Group). The general contractor under the EPC formula is a consortium of Metlen (formerly Mytilineos) and Siemens Energy. The value of the investment is approx. PLN 2 billion. The cornerstone was laid in May 2023, and the original commissioning date (2025) was postponed to 2026. In 2026 the unit entered the start-up phase and delivered energy to the national power grid for the first time.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
Slip: +12 mo. vs. the original date
- Construction start 18 May 2023
- Original date 2025
- Current date 2026
Change history
- Jul 2026 stage: commissioning
- 18 May 2023 stage: construction
Significance
The new unit increases the dispatchable, flexible generation capacity of the national system (operating in the range from just under 40% to 100% of capacity), supporting the balancing of the system amid a growing share of renewables and replacing high-emission coal capacity. The unit is covered by capacity-market support (a capacity obligation of 518 MW from 2026).
Sources 6 · 5 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- wGospodarce.pl 18 May 2023CostConstruction startStage historyInvestor
Cost „ok. 2 mld zł"
Construction start „18 maja 2023"
- Metlen Energy & MetalsInvestorOriginal date
Investor „SPV CCGT Grudziądz Sp z o.o. (owned entirely by Energa S A, part of Orlen Group)"
Original date „38 months after the signing of the contract"
locations[0] „Grudziadz, Poland"
- CCGT Grudziądz Sp. z o.o. 8 Jan 2026StageStatusInvestor
- Inwestycje.pl 13 Jul 2026StatusStageStage history
Status „Pierwszy zapłon turbiny gazowej oraz synchronizacja generatora z krajową siecią elektroenergetyczną to kluczowe etapy rozruchu bloku gazowo-parowego."
stage_events[1] „energia z CCGT Grudziądz po raz pierwsz trafiła do systemu"
- CCGT Grudziądz blisko rozruchu. Już w przyszłym roku będzie pracować pełną parą i gazem ↗ archived ✓Zawsze Pomorze 11 Jul 2025SignificanceCost
name.pl „563 MW netto"
Significance „mogący pracować w zakresie od niespełna 40% do 100% mocy z zachowaniem wszystkich standardów emisyjnych"
- WysokieNapiecie.pl 2026Current date
Current date „Bloki CCGT w Grudziądzu i Ostrołęce ruszą w I poł. 2026, być może w I kw. 2026"