CCGT Grudziądz gas-and-steam power plant (Unit I, 563 MW)

under construction stage: commissioning delayed
2.0 bn PLN
estimate · data from 2025 ≈ 2.0 bn PLN (value-by-stage, est., nominal)

The CCGT Grudziądz gas-and-steam unit (Unit I) with a net capacity of approx. 563 MW, built by the company CCGT Grudziądz of the Energa Group (Orlen Group). The general contractor under the EPC formula is a consortium of Metlen (formerly Mytilineos) and Siemens Energy. The value of the investment is approx. PLN 2 billion. The cornerstone was laid in May 2023, and the original commissioning date (2025) was postponed to 2026. In 2026 the unit entered the start-up phase and delivered energy to the national power grid for the first time.

How it went

Assessment: too early to assess. Signals only where documented.

Delivery partial
Schedule delayed

Timeline

Slip: +12 mo. vs. the original date

  1. Construction start 18 May 2023
  2. Original date 2025
  3. Current date 2026

Change history

  • Jul 2026 stage: commissioning
  • 18 May 2023 stage: construction

Significance

The new unit increases the dispatchable, flexible generation capacity of the national system (operating in the range from just under 40% to 100% of capacity), supporting the balancing of the system amid a growing share of renewables and replacing high-emission coal capacity. The unit is covered by capacity-market support (a capacity obligation of 518 MW from 2026).

Sources 6 · 5 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. wGospodarce.pl 18 May 2023
    CostConstruction startStage historyInvestor
    Cost „ok. 2 mld zł"
    Construction start „18 maja 2023"
  2. Metlen Energy & Metals
    InvestorOriginal date
    Investor „SPV CCGT Grudziądz Sp z o.o. (owned entirely by Energa S A, part of Orlen Group)"
    Original date „38 months after the signing of the contract"
    locations[0] „Grudziadz, Poland"
  3. CCGT Grudziądz Sp. z o.o. 8 Jan 2026
    StageStatusInvestor
  4. Inwestycje.pl 13 Jul 2026
    StatusStageStage history
    Status „Pierwszy zapłon turbiny gazowej oraz synchronizacja generatora z krajową siecią elektroenergetyczną to kluczowe etapy rozruchu bloku gazowo-parowego."
    stage_events[1] „energia z CCGT Grudziądz po raz pierwsz trafiła do systemu"
  5. Zawsze Pomorze 11 Jul 2025
    SignificanceCost
    name.pl „563 MW netto"
    Significance „mogący pracować w zakresie od niespełna 40% do 100% mocy z zachowaniem wszystkich standardów emisyjnych"
  6. WysokieNapiecie.pl 2026
    Current date
    Current date „Bloki CCGT w Grudziądzu i Ostrołęce ruszą w I poł. 2026, być może w I kw. 2026"