Clinical and Teaching Centre of the Medical University of Łódź – Stage II (CKD2) with the Academic Oncology Centre
The second stage of construction of the Clinical and Teaching Centre (CKD2) of the Medical University of Łódź is a multi-year investment programme carried out on Pomorska street with a budget of PLN 798.5 million, financed mainly from the state budget (PLN 625.2 million), the university's own funds (PLN 128.8 million), and funds of the Central Clinical Hospital of the Medical University (PLN 44.5 million). The investor is the Medical University of Łódź, and the implementation period covers the years 2018–2026. The contract with the consortium of contractors Warbud and Budomal was signed on 27 August 2020, originally with a completion deadline of 865 days (completion planned for 2023), which was subsequently pushed to 2026. The scope includes the development of the previously unfinished part of buildings A1 and A2 for a new medical programme, the expansion of the operating block and imaging diagnostics, and the creation of a total of 21 medical units, including the Academic Oncology Centre and the Academic Gynaecology and Obstetrics Centre. The total area is 42,083 m², of which 7,177 m² is a new building. The investment is at an advanced stage: an occupancy permit was obtained for building A1, and highly advanced finishing works and acceptance procedures with the investor were underway on building A2.
How it went
No outcome assessment: this record carries none on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 3 years: originally 2023, currently 2026.
Timeline
- Construction start27 Aug 2020
- Original date2023
- Current date2026
Change history
- Aug 2020stage: construction
Significance
CKD2 is one of the largest hospital and academic investments in Łódź and the Łódź region, concentrating the previously dispersed medical and teaching units of the Medical University into a single complex on Pomorska street. A key outcome of the programme is the creation of the Academic Oncology Centre and the Academic Gynaecology and Obstetrics Centre, together with the expansion of the operating block and imaging diagnostics and a total of 21 medical units over an area of more than 42,000 m². The investment, worth PLN 798.5 million and financed mainly from the state budget, also illustrates the schedule slippage and cost increases typical of large hospital projects: the originally assumed completion in 2023 was pushed to 2026, and the programme's value rose from approx. PLN 576 million (2020) to PLN 798.5 million. In mid-2026 the investment was in its final phase – building A1 obtained an occupancy permit, and building A2 was at the stage of advanced finishing works and acceptance procedures.
Sources 8 · 5 independent · 6 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- [1]Drugi etap budowy Centrum Kliniczno-Dydaktycznego Uniwersytetu Medycznego w Łodzi wraz z Akademickim Ośrodkiem Onkologicznym (CKD2) ↗archived ✓Uniwersytet Medyczny w ŁodziCostCurrent dateFunding
NameNazwa inwestycji: Drugi etap budowy Centrum Kliniczno-Dydaktycznego Uniwersytetu Medycznego w Łodzi wraz z Akademickim Ośrodkiem Onkologicznym (CKD2)
CostBudżet projektu: 798,5 mln zł
Current dateOkres realizacji projektu: 2018 – 2026
LocationLokalizacja projektu: 92–213 Łódź, ul. Pomorska 251
FundingBudżet Państwa: 625,2 mln zł
Fundingśrodki własne uczelni: 128,8 mln zł
Fundingśrodki SP ZOZ Centralnego Szpitala Klinicznego Uniwersytetu Medycznego w Łodzi: 44,5 mln zł
- Centrum Kliniczno-Dydaktyczne UM w Łodzi
- [3]II etap budowy Centrum Kliniczno-Dydaktycznego Uniwersytetu Medycznego w Łodzi wraz z Akademickim Ośrodkiem Onkologicznym ↗archived ✓Ministerstwo Zdrowia
- TuLodz.pl29 Aug 2020
- Warbud SA2020Original date
Original datePo zakończeniu rozbudowy – w 2023 roku - kilkanaście oddziałów diagnostycznych i laboratoryjnych znajdujących się na terenie miasta Łodzi zostanie przeniesionych do kampusu
- Centrum Kliniczno-Dydaktyczne UM w ŁodziAug 2020InvestorConstruction start
Investor · Construction start27 sierpnia br. Uniwersytet Medyczny w Łodzi podpisał umowę z konsorcjum firm Warbud i Budomal
year taken from the source's publication date (Aug 2020)
- Warbud SAStatusStage
StatusObecnie trwają odbiory z Inwestorem oraz usuwanie usterek. Mocno zaawansowane są prace wykończeniowe na obiekcie A2.
StagePozwolenie na użytkowanie obiektu A1 uzyskaliśmy już na początku kwietnia. Obecnie trwają odbiory z Inwestorem oraz usuwanie usterek. Mocno zaawansowane są prace wykończeniowe na obiekcie A2.
- Nauka w Polsce (PAP)24 Sep 2025Status
StatusTe inwestycje były dla nas wyjątkowo ważne, ponieważ w naszym szpitalu już niebawem powstanie Akademicki Ośrodek Onkologii.