CCGT Ostrołęka combined-cycle gas power plant
A combined-cycle gas turbine unit with a capacity of 745 MWe net being built in Ostrołęka (Mazowieckie Voivodeship) by CCGT Ostrołęka sp. z o.o. of the Energa Group (ORLEN Group), after the coal-fired Ostrołęka C project was abandoned and the technology switched to gas. The general contractor under the EPC formula is GE Power and General Electric Global Services; the notice to proceed (NTP) was issued on 24 March 2022. In October 2023 an addendum raised the contractor's estimated remuneration from approx. PLN 2.5 to approx. PLN 2.85 billion net, among other reasons due to the effects of the war in Ukraine. The contractual date for signing the provisional acceptance certificate was set at 31 December 2025; in December 2025 the unit entered the cold-start phase, and as of March 2026 the project was approximately 90% complete, with the first firing of the gas turbine planned for mid-2026 and an operational milestone in the second half of 2026. The unit will be fuelled by natural gas from the Poland-Lithuania interconnector via a pipeline approximately 28 km long.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
Slip: +6 mo. vs. the original date
- Construction start 24 Mar 2022
- Original date 31 Dec 2025
- Current date 2026
Change history
- 12 Dec 2025 stage: commissioning
- 24 Mar 2022 stage: construction
Significance
The 745 MW unit, thanks to its high operational flexibility, is intended to support the security of the National Power System during the energy transition, in line with the goals of Poland's energy policy up to 2040. As a source fuelled by high-methane natural gas from the Poland-Lithuania interconnector, it replaces the abandoned coal-fired Ostrołęka C project and closes the dispatchable capacity balance in north-eastern Poland.
Sources 6 · 4 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Bankier.pl 24 Mar 2022Construction startStage historyDescription
Construction start „Spółka CCGT Ostrołęka wydała polecenie rozpoczęcia prac związanych z budową elektrowni gazowo-parowej"
Description „745 MWe netto"
Description „Generalnym wykonawcą jest GE Power oraz General Electric Global Services"
- Money.pl 3 Oct 2023CostOriginal dateDescription
Cost „szacowane wynagrodzenie General Electric Global Services za wykonanie elektrowni CCGT w Ostrołęce wzrośnie z ok. 2,5 mld zł netto do ok. 2,85 mld zł netto"
Original date „Termin podpisania świadectwa obioru warunkowego elektrowni został ustalony na 31 grudnia 2025 roku."
- Energa SA (biuro prasowe) 31 Jan 2025DescriptionSignificance
Significance „gaz ziemny z interkonektora Polska-Litwa"
- Energa SA (biuro prasowe) 12 Dec 2025StatusStageStage historySignificance
Status „Rozpoczęcie tzw. zimnego rozruchu bloku gazowo-parowego otwiera ostatni etap realizacji inwestycji"
Stage „Blok CCGT Ostrołęka wszedł w fazę rozruchów"
- CCGT Ostrołęka sp. z o.o.InvestorStatus
Investor „CCGT Ostrołęka Sp. z o.o."
locations „ul. Krańcowa 1K / Budynek B, 07-401 Ostrołęka"
- eOstroleka.pl 20 Mar 2026progress.pctCurrent dateStatusDescription
Status „oba projekty - Ostrołęka i Grudziądz - są gotowe w około 90%"
Current date „uzyskanie operacyjnego kamienia milowego - w drugiej połowie 2026 roku"