A combined-cycle gas power plant of about 561 MWe net in Gdańsk's Rudniki district, built by CCGT Gdańsk, a wholly owned subsidiary of Energa (Orlen Group). The turnkey design-and-build contract was signed on 15 September 2025 with a consortium of Polimex Mostostal and Siemens Energy, at an estimated value of about PLN 3 billion. The foundation stone was laid on 11 May 2026. In October 2026 Energa reported completing the foundation slabs for the turbine set and the heat recovery boiler. Commissioning is planned for 2029.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Construction startMay 2026
- Original date2029
- Current date2029
Change history
- May 2026stage: construction
Significance
It will be the first generating unit of this size in the Tricity area. The project has a 17-year capacity-market contract guaranteed from 2029. Cooling water is to come from the Gdańsk Wschód wastewater treatment plant, which the Ministry of Energy describes as a solution unique in the Polish power sector.
Sources 5 · 5 independent
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Strefa Inwestorów15 Sep 2025
- WysokieNapiecie.pl (ISBnews)15 Sep 2025CostOriginal dateFunding
Costelektrowni gazowo-parowej (CCGT) o mocy około 561 MWe netto za szacunkową kwotę ok. 3 mld zł
Original datew okresie następującym po oddaniu elektrowni do eksploatacji. Harmonogram realizacji projektu przewiduje rozpoczęcie prac budowlanych w 2025 roku, natomiast oddanie elektrowni do eksploatacji w 2029 roku
FundingŁączne przewidywane przychody spółki z tytułu tego kontraktu w okresie jego obowiązywania mogą wynieść co najmniej ok. 4,8 mld zł
- Ministerstwo Energii (gov.pl)11 May 2026Stage
StageRozpoczyna się budowa elektrowni gazowo-parowej CCGT Gdańsk.
- Gdańsk.pl11 May 2026Construction startCurrent dateInvestor
Construction startW poniedziałek, 11 maja, wmurowano kamień węgielny pod tę inwestycję.
Current dateElektrownia ma być gotowa w 2029 r.
InvestorZa inwestycję odpowiada powołana specjalnie w tym celu spółka CCGT Gdańsk , w której 100 procent udziałów posiada Energa S.A
- StockWatch.pl13 Oct 2026Status
StatusEnerga ukończyła wykonanie płyt fundamentowych pod najważniejsze urządzenia bloku gazowo-parowego o mocy ok. 0,6 GW w Gdańsku.