CAMILA – National Constellation of Earth Observation Satellites (ESA/NRP)
CAMILA (Country Awareness Mission in Land Analysis) is a national Earth observation satellite constellation being built by Creotech Instruments S.A. as the main contractor. The constellation was ordered by the Ministry of Development and Technology, which entrusted the conduct and management of the tender to the European Space Agency (ESA). The original contract from April 2025, valued at approximately EUR 51.9 million, covers at least three satellites (radar, high-resolution optical, and lower-resolution optical) together with a ground segment for satellite control and data processing. According to ESA, more than 90 percent of the solution consists of technology developed in Poland, and the intellectual property rights remain in the country. In November 2025 the contract was expanded to more than EUR 59 million, adding a fourth satellite on the HyperSat platform and extending the schedule. It is the largest contract ever signed between ESA and a Polish entity.
How it went
No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section
Timeline
- Announced15 Apr 2025
- Original dateDec 2027
- Current dateNov 2029
Change history
- 15 Apr 2025stage: announced
Significance
The constellation is intended to give Poland its own sovereign Earth observation capabilities, both radar and optical, together with a domestic ground segment for satellite control and data processing. Thanks to the more than 90-percent share of domestic technology and the retention of intellectual property rights in Poland, the project strengthens the technological independence of the Polish space sector and engages several hundred specialists across the country.
Sources 6 · 4 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- [1]Creotech Instruments secures €52 million ESA contract to build Polish satellite constellation CAMILA ↗archived ✓Creotech Instruments15 Apr 2025StatusStageStage historyAnnouncedOriginal date
Status · Original dateThe project will run from April 2025 to December 2027.
StageCreotech will provide a national constellation of at least three Earth observation satellites along with dedicated ground infrastructure.
Stage history · AnnouncedSigned on 15 April, the contract covers the development of three satellites
year taken from the source's publication date (15 Apr 2025)
- SpaceNews16 Apr 2025
- [3]Creotech Instruments podpisał umowę z ESA na realizację projektu Camila o wartości niemal 52 mln euro ↗archived ✓Nauka w Polsce (PAP)15 Apr 2025CostInvestor
CostCałkowita wartość projektu wynosi 51,9 mln euro, z czego 25,6 mln euro przypada na Creotech Instruments.
Investornarodowa konstelacja satelitów została zamówiona przez Ministerstwo Rozwoju i Technologii, które wybrało Europejską Agencję Kosmiczną (ESA) do realizacji i zarządzania przetargiem.
- Creotech InstrumentsNov 2025Current date
Current dateCreotech Instruments now plans to complete its part of the CAMILA project in November 2029
- SpaceNews2024
LocationAt our facility in Piaseczno, close to Warsaw, where we make 10 microsatellites per year, our capacities are fully booked.
- Funding
FundingPoland will fund the expected €85 million (378 million zloty) costs while the ESA will help the country with the design, construction, launch and commissioning of the satellites.