Combined-Cycle Gas Units at the Kozienice Power Plant (2x CCGT, 1336 MW)
The construction of two combined-cycle gas units using CCGT technology with a total installed gross capacity of approximately 1,336 MWe at the Kozienice Power Plant in Świerże Górne. The investment is being carried out by Enea Elkogaz of the Enea Group, and the general contractor for the turnkey (EPC) contract is the Turkish company Calik Enerji; the technology supplier is GE Vernova. The construction site was handed over to the contractor on 2 January 2026, and the handover of the units for operation is planned for 31 March 2029 and 30 June 2029. Financing of PLN 6.95 billion was provided in December 2025 by a consortium of Polish banks led by Bank Gospodarstwa Krajowego. The project replaces worn-out coal-fired capacity at Kozienice.
How it went
Assessment: too early to assess. Signals only where documented.
Timeline
- Construction start 2 Jan 2026
- Original date 30 Jun 2029
- Current date 30 Jun 2029
Change history
- 2 Jan 2026 stage: construction
Significance
The two combined-cycle gas units with a capacity of approximately 1,336 MWe are intended to replace aging coal-fired capacity at the Kozienice Power Plant, providing a stable, controllable energy source supporting the security of the National Power System during the transition period. The project secured capacity market support for 17 years from 2029, and the share of Polish companies in its execution is estimated at approximately 75%, giving a development impulse to the central-eastern Poland region.
Sources 5 · 4 archived
Every fact on this card comes from the sources below. Next to each source — which fields it supports.
- Ruszyła budowa bloków gazowo-parowych w Kozienicach. Enea stawia na polskie kompetencje i polskie firmy ↗ archived ✓Grupa Enea 16 Feb 2026StatusStageStage historyCostInvestorConstruction startCurrent dateOriginal date
Status „Ruszyła budowa bloków gazowo-parowych w Kozienicach"
Stage „Po oficjalnym przekazaniu 2 stycznia 2026 roku terenu budowy generalnemu wykonawcy, zrealizowano już komplet badań geotechnicznych."
stage_events[0].date „Po oficjalnym przekazaniu 2 stycznia 2026 roku terenu budowy generalnemu wykonawcy"
Current date „Planowany termin przekazania bloków do eksploatacji to 31 marca 2029 r. oraz 30 czerwca 2029 r."
Cost „finansowanie w wysokości 6,95 mld zł (w tym kredyt inwestycyjny 6,45 mld zł oraz 0,50 mld zł na kredyty VAT i obrotowy)"
Investor „Enea Elkogaz, spółka z Grupy Enea odpowiedzialna za inwestycję"
- Parkiet 16 Feb 2026CostCurrent date
- WNP.pl 16 Feb 2026Status
- Bankier.pl / PAP 16 Feb 2026StageCurrent date
- Wikipedia
locations[0].voivodeship „Znajduje się w Świerżach Górnych koło Kozienic w woj. mazowieckim."