Dolna Odra Combined-Cycle Gas Units (Gryfino) — 2x ~700 MW

completed stage: operational delivereddelayed
4.7 bn PLN
contract value · data from 2024 ≈ 4.7 bn PLN (value-by-stage, est., nominal)

The construction of two combined-cycle gas (CCGT) units, no. 9 and no. 10, at the Dolna Odra Power Plant Complex in Nowe Czarnowo near Gryfino (Zachodniopomorskie Voivodeship), belonging to PGE Górnictwo i Energetyka Konwencjonalna of the PGE Group. Each unit has a rated gross electrical capacity of 683 MWe, for a total of approximately 1,366 MW of new gas-fired capacity. The investment was carried out by a consortium of General Electric (GE Vernova) as leader and Polimex Mostostal. Unit no. 9 was handed over for operation in August 2024, and unit no. 10 at the end of October 2024 — with a significant delay relative to the original deadline of December 2023.

How it went

Assessment: provisional. Signals only where documented.

Delivery delivered
Schedule delayed
Utilisation in use
Scope as announced
gross electricity production (H1 2025)
2,132,025.36 / 13,665,965 TWh (H1 2025) 16% utilisation

Timeline

Slip: +10 mo. vs. the original date

  1. Original date 11 Dec 2023
  2. Delivery 29 Oct 2024

Change history

  • 29 Oct 2024 stage: operational
  • 14 Aug 2024 stage: commissioning

Significance

The two combined-cycle gas units with a total capacity of approximately 1,366 MW replaced part of the aging coal-fired generating capacity and made the Dolna Odra power plant the largest gas-fired power plant in Poland. The investment strengthens security of energy supply in north-western Poland and provides flexible, dispatchable capacity balancing the growing share of renewable sources in the national power system.

Sources 7 · 4 archived

Every fact on this card comes from the sources below. Next to each source — which fields it supports.

  1. WNP.pl Aug 2024
    StatusStageCostInvestorOriginal dateStage history
    Status „14 sierpnia 2024 r. przekazały do eksploatacji blok gazowo-parowy nr 9"
  2. elektro.info Aug 2024
    InvestorStage history
    Investor „Nowym Czarnowie koło Gryfina (woj. zachodniopomorskie) ... należącej do Grupy PGE"
    locations[0].voivodeship „Nowym Czarnowie koło Gryfina (woj. zachodniopomorskie)"
  3. Wikipedia (pl)
    DeliveryStage historyInvestor
    Stage „29 października – oddanie do użytku bloku gazowego nr 10"
  4. Interia Biznes Aug 2024
    CostOriginal date
    Cost „Łączna wartość wszystkich zawartych umów wyniosła około 4,73 mld zł netto - czyli prawie 5,82 mld zł brutto."
    Original date „planowano, że inwestycja zostanie ukończona cztery lata później - 11 grudnia 2023 r."
  5. PGE GiEK (Zespół Elektrowni Dolna Odra) 30 Jan 2020
    Investor
  6. WNP.pl Mar 2026
    OutcomeUtilisation
    Utilisation „W I półroczu 2025 PGE Gryfino Dolna Odra wyprodukowała 2,13 TWh energii elektrycznej."
  7. Teraz Środowisko Oct 2024
    OutcomeUtilisation
    Utilisation „elektrownia pokryje ponad 5% krajowego zapotrzebowania na energię elektryczną (...) posiada obowiązujący od 2024 r. 17-letni kontrakt na aukcji rynku mocy"
    Scope „dwóch bloków gazowo-parowych o mocy 683 MW"