BW-100 coal-fired unit at Grupa Azoty Puławy

pausedstage: commissioning
PLN 1.2 billion
programme budget (multi-year) · data from 2023net or gross: not recorded≈ PLN 1.2 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of a cogeneration coal-fired unit with 100 MW of electric and 300 MW of thermal capacity at the Grupa Azoty Puławy plant. The contract with a consortium led by Polimex Mostostal was concluded on 25 September 2019, and completion was planned for the third quarter of 2022. After a 2023 annex the total project budget is PLN 1.23 billion. Start-up began in July 2022 and the guaranteed parameters were not reached. In January 2025, at 593 days of delay, Grupa Azoty Puławy terminated the contract for the unfinished scope. The dispute went to mediation in April 2026, and the company does not know whether or when the unit will start.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, one carries no assessment yet, 3 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Construction start2019
  2. Original dateSep 2022

Change history

  • Jul 2022stage: commissioning

Significance

The unit was to replace two old units from the 1960s. It is not operating commercially. Start-up revealed unstable operation, numerous failures and failure to reach the guaranteed parameters. The company is running tenders to complete start-up and is talking to the suppliers of the turbine set and the flue-gas desulphurisation plant. According to Parkiet, if the unit does not start, the company may lose over a billion zloty on the investment.

Sources 3 · 3 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Parkiet4 Feb 2026
    StatusStageCostConstruction start
    StatusNie wiadomo kiedy i czy w ogóle zostanie uruchomiony ostatni praktycznie już wybudowany blok węglowy w Polsce
    Stagenieosiągnięcie parametrów gwarantowanych w rozruchu, który rozpoczął się w lipcu 2022 r.
    Costw 2023 r. został podpisany aneks do umowy, zwiększający wynagrodzenie przysługujące wykonawcy do kwoty ponad 1,196 mld zł, co spowodowało zwiększenie całkowitego budżetu projektu do 1,23 mld zł
    Construction startBudowę rozpoczęto w 2019 r.
  2. XYZ12 May 2026
    Original dateInvestor
    Original dateTermin oddania przypadał na trzeci kwartał 2022 roku.
    InvestorKonflikt dotyczy kontraktu na budowę bloku węglowego BW100
  3. Energetyka2425 Oct 2024
    Investor
    Investorprzekazał Grupie Azoty Zakłady Azotowe Puławy odpowiedzi