⚡Energystrategic

Gryfino Battery Energy Storage System (BESS, 400 MW / 800 MWh)

in preparationstage: tender
PLN 1.1 billion
contract value · data from Apr 2026incl. VAT≈ PLN 1.1 billion (value-by-stage, est., nominal)funding: capacity marketLimitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

A battery energy storage system of up to 400 MW and at least 800 MWh, to be built by PGE Energia Odnawialna (PGE Group) at the Dolna Odra power plant in Nowe Czarnowo near Gryfino, Zachodniopomorskie Voivodeship. The tender was launched in August 2025; the contracting authority's budget was close to PLN 969 million gross, and all three bids exceeded it. In April 2026 a design-and-build contract worth PLN 1.142 billion gross was signed with a consortium of Polish companies, SPEC BAU POLSKA and El Professional; the battery technology will be supplied by Fluence. Commissioning is planned for the end of 2028.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Original date2028
  2. Current date2028

Change history

  • Aug 2025stage: tender

Significance

Once in operation, it is set to be the largest battery energy storage facility in Poland by installed power. It is meant to store surplus energy from wind and solar farms and release it to the grid at times of higher demand. The project holds a 17-year capacity market contract with an obligation of close to 121 MW from the start of 2029.

Sources 8 · 6 independent · 6 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Gramwzielone.pl8 Aug 2025
    LocationInwestycja zostanie zrealizowana przy Elektrowni Dolna Odra w Nowym Czarnowie koło Gryfina.
  2. WysokieNapiecie.pl31 Oct 2025
    Original dateFunding
    Original dateObiekt ma zostać przekazany do eksploatacji w ciągu 33 miesięcy od wejścia umowy w życie kontraktu z wykonawcą lub do 30 września 2028 roku.
    FundingDla przedsięwzięcia PGE zabezpieczyła przychody w postaci 17-letniej umowy na rynku mocy.
  3. Gramwzielone.pl15 Apr 2026
    CostInvestor
    CostWartość zamówienia wynosi 1,142 mld zł brutto.
    InvestorNależąca do grupy PGE spółka PGE Energia Odnawialna oficjalnie wybrała wykonawcę magazynu energii o docelowej mocy 400 MW i pojemności minimum 800 MWh
  4. Energetyka2429 Apr 2026
    Current date
    Current dateUruchomienie Magazynu Energii Gryfino planowane jest na koniec 2028 roku.
  5. SPEC BAU POLSKA30 Apr 2026
  6. wnp.pl29 Apr 2026
  7. igryfino.pl / PAP MediaRoom9 Jun 2026
  8. Gramwzielone.pl23 Sep 2026
    StatusStage
    StatusW kwietniu br. PGE Energia Odnawialna podpisała umowę z generalnym wykonawcą – konsorcjum dwóch polskich firm: Spec Bau Polska sp. z o.o. i El Professional sp. z o.o.
    StageObecnie trwają prace nad dokumentacją projektową, w tym nad projektem podstawowym i projektami budowlanymi.