Aegis Ashore Missile Defense Base at Redzikowo

completedstage: operationaldelivereddelayedover budget
USD 900 million
estimate · data from 2024net or gross: not recorded≈ PLN 3.6 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

The U.S. Aegis Ashore missile defense base at Redzikowo near Słupsk (Pomorskie Voivodeship), the land-based component of the Aegis system and part of NATO's ballistic missile defense (BMD/EPAA) alongside the twin installation at Deveselu in Romania. Construction was inaugurated on 13 May 2016; the facility reached operational status on 15 December 2023, and its official opening took place on 13 November 2024. The installation, equipped with launchers for SM-3 interceptor missiles, is designed to detect, track, and engage medium- and intermediate-range ballistic missiles in defense of Alliance territory.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduledelayed[3]
Budgetover budget[5]

Timeline

Slip: about 6 years vs. the original date (given as a year)

  1. Construction start13 May 2016
  2. Original date2018
  3. Delivery13 Nov 2024

Change history

  • 13 Nov 2024stage: operational
  • 15 Dec 2023stage: commissioning
  • 13 May 2016stage: construction

Significance

Redzikowo is one of two land-based interceptor sites of the Aegis Ashore system in Europe (alongside Deveselu in Romania), completing NATO's ballistic missile defense architecture on the Alliance's eastern flank. With the achievement of readiness, the base extends protection against medium- and intermediate-range ballistic missiles to the northern part of the continent, and it is staffed by U.S. Navy personnel operating within NATO structures.

Sources 8 · 6 independent · 5 archived

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. NATO10 Jul 2024
    StatusInvestorDelivery
    Status · DeliveryA new U.S. ballistic missile defence site in Redzikowo, Poland is now operational and available for the defence of the Alliance.
    InvestorKey elements of NATO’s missile shield include the two U.S. Aegis Ashore sites in Poland and Romania along with U.S navy destroyers out of Rota, Spain
  2. Wikipedia15 Jul 2026
    StageConstruction startStage historyDeliveryStatus
    Stage · Stage historybaza osiągnęła status operacyjny 15 grudnia 2023
    Construction start · Stage historyOficjalna inauguracja budowy tarczy antyrakietowej w Redzikowie odbyła się 13 maja 2016
    Stage history · Delivery · StatusOficjalne otwarcie bazy miało miejsce 13 listopada 2024
    Locationokolicach Redzikowa na terytorium Rzeczypospolitej Polskiej, w województwie pomorskim
  3. money.pl13 Nov 2024
    Original dateCostSchedule
    Original date · SchedulePierwotnie miała być oddana do użytku w 2018 r.
    CostKoszt inwestycji szacowany jest na 800-900 mln dol.
  4. Biuro Bezpieczeństwa Narodowego (bbn.gov.pl)13 Nov 2024
  5. MILMAG2020
    Budget
    Budgetthe construction cost increased by 13%, which means that additional $96 million will have to be allocated to the project. In result, the general cost of the Aegis Ashore programme in Poland will exceed $844 million.
  6. Wikipedia15 Jul 2026