120 mm M120 Rak self-propelled mortar: company fire modules (2016 contract)
On 28 April 2016 the Armament Inspectorate signed a contract with a consortium of Huta Stalowa Wola S.A. and Rosomak S.A. for the delivery of components for eight Rak company fire modules (KMO): 64 M120K 120 mm self-propelled mortars on a wheeled chassis and 32 AWD artillery command vehicles on a wheeled chassis. The gross contract value was PLN 968,319,188 (approx. PLN 968.3 million). Delivery of the ordered equipment was planned for 2017-2019 (components for two modules in 2017, and three complete sets each in 2018 and 2019). On 15 October 2019 the last, eighth company fire module left Huta Stalowa Wola, with which HSW completed the contract of 28 April 2016; the equipment was issued, among others, to the 12th Mechanised Brigade in Szczecin. The M120K mortar is built on the domestically produced Rosomak wheeled chassis, and the Rak modules are a product of the Polish defence industry (Huta Stalowa Wola / PGZ Group).
How it went
Assessment: settled, as of 25 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section
Timeline
- Announced28 Apr 2016
- Original date2019
- Delivery2019
Significance
The contract of 28 April 2016 launched serial production and the introduction into the Polish Armed Forces of the 120 mm M120 Rak self-propelled mortar, a new class of fire support weapon built on the domestically produced Rosomak wheeled chassis. Delivery of eight company fire modules (a total of 64 M120K mortars and 32 AWD artillery command vehicles) in 2017-2019 built the first core of Rak sub-units in Polish mechanised brigades and consolidated the artillery production capability of the domestic defence industry centred on Huta Stalowa Wola.
Sources 6 · 5 independent · 4 archived
Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Zespół Badań i Analiz Militarnych / Wojsko i Technika2017CostOriginal dateInvestor
Cost28 kwietnia 2016 r. Jej wartość brutto to 968 319 188 PLN
Original datedostawy zamówionego sprzętu mają zostać zrealizowane w latach 2017–2019 (w 2017 r. elementy dwóch modułów, w 2018 i 2019 r. po trzy komplety)
Investorzostała zawarta pomiędzy Inspektoratem Uzbrojenia a konsorcjum w składzie Huta Stalowa Wola S.A. i Rosomak S.A.
- DziennikZbrojny.pl1 May 2019Announced
Announcedumowy o wartości 968,3 mln PLN brutto zawartej 28 kwietnia 2016 roku z Hutą Stalowa Wola S.A.
- Zespół Badań i Analiz Militarnych16 Oct 2019StatusStageDeliverySchedule
Status · DeliveryTymi dostawami Huta Stalowa Wola S.A. kończy realizację umowy zawartej 28 kwietnia 2016 roku na produkcję wyposażenia dla ośmiu KMO RAK.
StageSprzęt znajdzie się na wyposażeniu 12. Brygady Zmechanizowanej w Szczecinie.
Delivery15 października br. Hutę Stalowa Wola S.A. opuścił ostatni już VIII Kompanijny Moduł Ogniowy
year taken from the source's publication date (16 Oct 2019)
ScheduleHSW S.A. bez opóźnień, zgodnie z terminami zawartymi w umowie przekazuje do jednostek Wojska Polskiego już ósmy kompanijny moduł ogniowy.
- Radar / Rzeczpospolita28 Apr 2020
- Polska Grupa Zbrojeniowa30 Jun 2017Funding
FundingPrzyjęcie do służby na wyposażeniu Sił Zbrojnych RP elementów pierwszego kompanijnego modułu ogniowego moździerza samobieżnego „Rak” na podwoziu kołowym oznacza rozpoczęcie pierwszej fazy dostaw sprzętu zamówionego przez Inspektorat Uzbrojenia MON.